Action Plan – 1st year. Nataša Urbančíková Faculty of Economics Technical University of Košice. Activity 4.1: Preparation of dissemination plan Resp: TUKE Deadlines: for UA partners fill in template–June 30, 2012 for 4.1 – August 31, 2012. Activity 5.1: Project team establishment
E N D
Action Plan – 1st year Nataša Urbančíková FacultyofEconomics TechnicalUniversityof Košice
Activity 4.1:Preparation of dissemination plan • Resp: TUKE • Deadlines: • for UA partners fill in template–June 30, 2012 • for 4.1 – August 31, 2012
Activity 5.1: Project team establishment • Resp: TUKE • Deadlines: • for UA partners–June 30, 2012 • Name of WP leaders, benchmarkign group, AP • for 5.1 – July 31, 2012
Activity 5.2 Preparation and maintenance of communication infrastructure Web site preparation • Resp: TUKE • Deadlines: • for UA partners–July 31, 2012 • Info on web site including translations • for 5.2 – August 31, 2012
Activity 5.3 Preparation of a quality manual and project monitoring manual • Resp: YIC, Ukraine • Deadlines: • for 5.3 – August 31, 2012 • Please send the draft till July 31, 2012
Activity 1.1 -1.7Analyses –altogether 7 • Methodology: resp: TUKE • Deadlines: • FOR METHODOLOGY - till September 30, 2012
Activity 1.1 Analysis of economic and technological development in the partner regions • The analyses will be carried out in both countries. • TU Kosice provides analyses in Slovakia and • ZAIID in Ukraine. • TU Kosice will be responsible for final cross border analyses.Deadlines: June 30, 2013
Activity 1.2 Analysis of existing R&D policies, plans and activities at the regional level, including institutions to promote R&D. • The analyses will be carried out in both countries. • TUKE provides analyses in Slovakia and • ZAIID in Ukraine • ZAIID will be responsible for final cross border analyses.Deadlines: June 30, 2013
Activity 1.3 Analysis of regional (subnational) capacity to produce, disseminate and use knowledge • The analyses will be carried out in both countries. • TUKE provides analyses in Slovakia and • ZAIID in Ukraine • TU Kosice will be responsible for final cross border analyses.Deadlines: June 30, 2013
Activity 1.4 Analysis of public and private R&D institutions operating at regional level • The analyses will be carried out in both countries. • TU Kosice provides analyses in Slovakia and • ZAIID in Ukraine • ZAIID will be responsible for final cross border analyses.Deadlines: June 30, 2013
Activity 1.5 Analysis of small and medium-sized enterprises (SMEs) and large companies (LC) at the regional level, with significant potential and demand for research and development. • The analyses will be carried out in both countries. • TU Kosice provides analyses in Slovakia and • ZAIID in Ukraine • ZAIID will be responsible for final cross border analyses.Deadlines: June 30, 2013
Activity 1.6 Analysis of existing resources (financial entities) adequate funding for RDI in selected regions. • The analyses will be carried out in both countries. • TU Kosice provides analyses in Slovakia and • ZAIID in Ukraine • TU Kosice will be responsible for final cross border analyses.Deadlines: June 30, 2013
Activity 1.7 Regional analysis of the level of social capital in target regions, focusing on existing partnerships as a basis for future cross-border clusters and cluster initiatives • The analyses will be carried out in both countries. • TU Kosice provides analyses in Slovakia and • ZAIID in Ukraine • TU Kosice will be responsible for final cross border analyses.Deadlines: June 30, 2013
Activity 2.1 Establishment of a list of benchmarking indicators • The benchmarking indicators will be selected by TU Košice. The cooperation of both Ukrainian partners is needed. • TU Košice will be responsible for overall task. • Deadline: September 30, 2012 • Suggestionsfromeach partner forbenchmarking team: tillJune 30, 2012 (including CV)
Activity 3.1 Preparation of e-learning course on clusters and cluster initiatives • Respfor 3.1: ZAIID –deadline: -31.12.2012 • SENDING SUGGESTION on module titles and content to TUKE tillJuly 15, 2012 • ZAIIDwill be responsible for 2 modules preparation. • TUKE will be responsible for 2 modules preparation.
Activity 4.2 Preparation of database of key players for the development of cross-border clusters and cluster initiatives and their contacts • Duration:1.8.2012-30.10.2012 • Resp.:YIC, Ukraine • Sending template to SK: September 10, 2012
Activity 2.2 Identification of the differences and best practices in selected areas • Duration: November 1, 2012 – August 31, 2013 • The benchmarking will be carried out in both countries. • TU Košice provides benchmarking in Slovakia and • Youth Informational Centre in Ukraine • TU Košice will be responsible for overall task • TUKE willsendmethodologytillNovember 30, 2012
Activity 3.2 Implementation of the e-learning course on clusters and cluster initiatives • Duration: 1.1.2013-31.5.2013 • Resp.: ZAIID • SendingtemplateforcourseevaluationtillDecember 15, 2012 • The course delivery will be done separately in both countries by national lectors. • ZAAID will be responsible for course in Ukrainian language delivery. • TU Kosice will be responsible for Slovak language delivery.
Activity 4.3 Preparation of promotional materials • Duration:1.11.2012-31.12.2012 • Resp.:TU Kosice is responsible for 1st leaflet preparation. • UA TRANSLATION NEEDED:TUKE will send text till November 10, 2012 –translation till November 30, 2012
Activity 3.3 Implementation of two cross-border workshops • Duration: till 31. May 2013 – UA • Send us suggestions for data till December 31, 2012 • YIC, Ukraine will be responsible for workshop in Ukrainian language delivery.
Project Meetings: • 1st PM – UA – June 11, 2012 • 2nd PM – 22. February 2013, Kosice (Friday) ???