DCal / PHOS dummy Insertion (1/3). Any Pert or Grant planning should include all tasks / subsystems required for the goal: 1. Platform for Insertion Tooling 2. Insertion Tooling 3. Bridge 4. Shuttle for C side 5. Shuttle for A side 6. DCal extension devices
E N D
DCal / PHOS dummy Insertion (1/3) Any Pert or Grant planning shouldinclude all tasks/subsystemsrequired for the goal: 1. Platform for Insertion Tooling 2. Insertion Tooling 3. Bridge 4. Shuttle for C side 5. Shuttle for A side 6. DCal extension devices 7. DCal Support structure 8. DCalsupermodule 9. DCal extension 1/3 supermodule 10. PHOS module 11. Tooling and specificequipments for PHOS 12. Motorized system for displacement of detectors 13. Othersubsystems 14. Link to ALICE-LS1 schedule
DCal support structure load test (2/3) • Nominal loadingDCal+PHOS : (6*5.4) + (2*2.9) + (4*5.9) = 61.8 t • 7*4*1.25 = 35 t brownslots 9, 8, 10, 1135 t 57 % • 9*3.7 t = 33.30 t green slots 9, 8, 10, 11, 1268.3 t 111 % • Survey • 5*1*1.25 = 6.25 t brownslots 9, 8, 10, 1174.55 t 121 % • 6*1.85 = 11.10 t yellowslots 9, 10, 1185.65 t 139 % • Survey
Status (3/3) • Inquiriesstarted for rotator • DCalribs : on the way, stillexpectedat CERN first week of August • System to insert ribsinto L3 designed