Transmission Service Requests Overview. 2007 Transmission Summit July 31, 2007 New Orleans, LA. ICT TSR Responsibilities. Maintain, Administer, and Post a Queue for Transmission Service Requests. Long-term service requests ( ≥1 year ) or requests outside the Study Horizon (18 months)
E N D
Transmission Service Requests Overview 2007 Transmission Summit July 31, 2007 New Orleans, LA
ICT TSR Responsibilities • Maintain, Administer, and Post a Queue for Transmission Service Requests. • Long-term service requests (≥1 year) or requests outside the Study Horizon (18 months) • Schedule, send, receive, and validate all Study Agreements • System Impact Study Agreement (SISA) • Facilities Study Agreement (FSA) • Respond to any inquiries by the Transmission Service Customer
ICT TSR Responsibilities • Perform System Impact Study. • ICT writes the System Impact Study Report (SISR) • Post all study reports (SISR & FSR) and documentation as per Entergy’s Tariff. • Provide all notices to the customer as required by the Tariff.
ICT TSR Responsibilities • Review and validate the results of the Facilities Study. • Prepare the Facilities Study Report (FSR). • Classify upgrades as Base Plan or Supplemental as per Attachment T to Entergy’s Tariff. • Coordinate studies with any Affected Systems
Entergy TSR Responsibilities • Review System Impact Study Report (SISR) • Tender, enter into, and file all Transmission Service Agreements. • Enter into 3rd party Facilities Study Agreement (FSA) with ICT and Customer. • Perform Facilities Study
Transmission Service Requests (2007) • ICT has sent out 136 SISAs. • ICT has performed and posted 76 SISR. • ICT has 32 SIS in progress. • Entergy has performed 16 FSR. • Entergy has 3 FS in progress.