1 / 17

LHC-YETS 2015-2016 Feedback

Overview of the YETS maintenance and tests, including electrical, cooling and ventilation, cryogenics, and beam instrumentation activities.

hermann
Download Presentation

LHC-YETS 2015-2016 Feedback

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LHC-YETS 2015-2016Feedback 22nd March, 2016 Marzia Bernardini, on behalf of EN-ACE-OSS team

  2. YETS overview • The YETS started in Monday 14th December 2015 • LHC machine back to BE-OP on Friday 4th March 2016 • 1070 activities were declared via IMPACT • Average number of access per day  160, with pics up to 220 accesses per day • Questions: • Issues during access requests? • PAD & MAD? LHC machine Schedule for YETS, INDICO 512656

  3. The Frame - Maintenance and tests • The regular maintenance and tests have been realised during the YETS • Cooling & Ventilation • 3 weeks per point for the SF, SU, UWMechanical cleaning of the cooling towers, Mechanical maintenance, Bugs fixing • Intervention mostly on the surface, but also underground (US and UA) on the air handling units • Cryogenics • The maintenance was realised on all the cryoplants • Heavier maintenance and consolidation were realised in IP4 (A) & IP6 (A), heavy corrective maintenance (repairs) was needed in IP8 (B). • Before the beam, some operational tests were realised by the cryogenics team- Cross check of the maximum free power for BS in S23/S78 (twin cryoplants) -- Setting up of the nominal configuration for all sectorsd with BE-OP • During the YETS, to minimise the risk related to the Helium lost:- The LSSs and DFB were emptied and were in GHe at 20 K.- The Lhelium was kept in the arcs except sectors 7-8 and 8-1, which were emptied, and in cold stand by with GHe. • Questions: • CV: same duration for EYETS? Same approach (only surface & underground during TSs) • CRG: Same baseline for EYETS? No Lhelium in two sectors LHC machine Schedule for YETS, INDICO 512656

  4. The Frame - Maintenance and tests • Electrical • AUG tests were realised (except BA80, 81, 82 and 85) :- on the whole LHC machine, Meyrin, Prevessin, … • The annual test of the electrical backup network (CERN wide) • The Auto-transfer test (LHC, Meyrin, PS, PSB, …) • Alarms and access completed successfully • Annual tests of alarms: sirens, ODHs and evacuation alarms on the whole LHC Machine & Experiments • The DSO test was realised in the LHC prior to start the powering tests • Questions: • The impact of the AUG tests on the cryo conditions must be defined BEFORE the EYETS • Therefore the related tests must also be defined (for ex. ELQA) LHC machine Schedule for YETS, INDICO 512656

  5. The frame – Baseline as 14th December 2015 LHC machine Schedule for YETS, INDICO 512656

  6. YETS schedule overview • Main changes • ELQA campaign • Repair of transformer @P2 and impact on powering tests LHC machine Schedule for YETS, INDICO 512656

  7. 5th Axis Collimators Many thanks to all for the efforts and commitment ! • In B4R1 and B4R5 (QRL side), the survey and vacuum teams face difficulties to align the VAMDA vacuum modules. • The vacuum chambers VCDOA and VCRLS are very close to TCTPV and TCTPH and can limit the movement of the 5th axis  The chambers were moved closer to the collimators, without impact on the 5th axis strokes • The protection plaque between the collimator and the QRL in 4L1 have been removed after un interaction on the collimator movement • Lesson learned • Daily on site coordination needed LHC machine Schedule for YETS, INDICO 512656

  8. TDI replacement Excellent team work! Without delay! • TDI @P2 has been realigned (2 times) • TDI @P8 an additional realignment was realised after the bake-out, under vacuum, with a movement of 8 mm on radial direction (validated with VSC and SURVEY teams) • Following the realignment the RF fingers have lost contact with the RF screen • The problem was solved and a new bake out was performed LHC machine Schedule for YETS, INDICO 512656

  9. Beam Instrumentation • Installation of the tent in LSS4, to protect the BGV - EDMS LHC-BGV-EC-0004 • Provide mechanical protection • Protect the detector modules from external light • Reduce the air dew point • The change of ferrite of the Beam Wire Scanner was also completed in LSS4 Tent for the BGV in LSS4 Wire scanner and ferrite LHC machine Schedule for YETS, INDICO 512656

  10. Activities related to Experiments • Point 1 • AFP RP Stations: • 2 new RP stations are installed in R1 • The triggering cables and control cables are installed in R1 and L1 • WCC: the installation of the New Water Cooled Cables for ALFA in RR13 and RR17 is completed and the circuits are validated by ELQA Atlas AFP RP station Atlas AFP cabling WCC in RR17 • Point 5 • CT-PPS timing & tracking s. 45 & 56 • The pulling of 480m of heliflex special low-loss RF cable for CT-PPS in Point 5 is completed Cabling for CT-PPS LHC machine Schedule for YETS, INDICO 512656

  11. Activities related to Experiments: Issue • Point 1: New Water Cooled Cables for ALFA in RR13 and RR17 EDMS LHC-LJ-EC-0044 • The cables were installed in RR13 and RR17. • Prior to start: • - DFBL were emptied (no Liquid Helium, T around 20K) • Exceptional authorisation has been delivered (EDMS 1564706) and risk analysis done maximum Helium release 2g/sec • VIC was realised • During the intervention a plate fell over the DFBLB (RR17)and damaged a ceramic insulation and the gaseous helium recovery line.The personnel safety was never affected (potential He release <<100g/s)and the applied procedures respect the CERN safety rules. • The repairing was realised without issues and the DBFLB was heated up to room temperature. • Outstanding item: • Cryo lock out???When and where??? • For the time being under the responsibility of Thomas Otto LHC machine Schedule for YETS, INDICO 512656

  12. Inspection of WCC • Water leaks detected on the WCC and WCT • Point 5 left (RR53)- WCC • DFB affected : DFBAI • Circuits affected  : RB • Cablesaffected  : 1508810A (DFLAS.7L5.2) • Point 2 left (RA23) - WCC • DFB affected : DFBAC • Circuits affected : RB & RQF • Cablesaffected : 1204995C (DFLAS.7L2.3), 1204997A (DFLAS.7L2.4) • & 1204985C (DFLAS.7L2.5) • Point 2 left (UA23) - WCC • DFB affected  : DFBAC • Circuits affected : RQD (extrémité du tube vers fourreau proche DFBAC) • Cablesaffected  : 1204988C (RQD.A12.C6) et 1204987A (RQD.A12.C1) • Point 8 left (UA83) - WCT • DFB affected : DFBAM • Circuits affected : WC tube RB • Outstanding Items • Definition of responsibilities between EN and CV LHC machine Schedule for YETS, INDICO 512656

  13. Other unexpected issues • Cables damaged during the opening LHC-CMS • Issue during the opening of the cable duct between CMS and LHC, for cabling campaign: • 5 cables were damaged: access system (1x), TOTEM (2X), ZDC (2X) • 3 cables of access system have been replaced by EN-EL • 2 cables for Experiments have been repaired by the Experiments • PM76 lift maintenance • Following the regular inspection and maintenance a major issue was found on PM76 Lift. • It was necessary to replace the Engine of the Lift and this needed 4 days for the intervention. Excellent management to find out solutions! LHC machine Schedule for YETS, INDICO 512656

  14. Other unexpected issues • Cables damaged during the opening LHC-CMS • Issue during the opening of the cable duct between CMS and LHC, for cabling campaign: • 5 cables were damaged: access system (1x), TOTEM (2X), ZDC (2X) • 3 cables of access system have been replaced by EN-EL • 2 cables for Experiments have been repaired by the Experiments • PM76 lift maintenance • Following the regular inspection and maintenance a major issue was found on PM76 Lift. • It was necessary to replace the Engine of the Lift and this needed 4 days for the intervention. Excellent management to find out solutions! LHC machine Schedule for YETS, INDICO 512656

  15. Other unexpected issues • BTV in TI8 • Unexplained screen movement in the IT8 BTVI88119 • BE-BI needed to check the integrity of the instrument, • for which the injection line needed to be vented (more than 500m) • Excellent reactivity of vacuum team! • EMT405/2U transformer in P2 • Tightness issue on the secondary side of the transformer (joints) • Decision to replace the joints (not the transformer) • Intervention scheduled from 2nd to 10th March •  New activity on the critical path! • Impact on Cryogenics and Schedule: • A Cryogenics reconfiguration from P2 to P18 was needed • The Powering tests were limited to the arcs 12 and 23 during the intervention • The timeslot for the cryogenics power test was unchanged (from 14th to 17th March) • The Powering tests in LSSs were postponed after the cryogenics power test • Sectors 12 and 23 have been ready for machine check out on Monday 21st March (+4 days WRT baseline) • Many thanks to EN-EL!!! LHC machine Schedule for YETS, INDICO 512656

  16. Conclusions • The YETS was fruitful for all the involved group • Many thanks for the work and the commitment!!! • No Accidents were reported and the access to the LHC was “fluid” • The preparation phase was very useful, and the same method will be used for the EYETS 2016-2017 • ECR ready by September 2016 • Coordination meetings with EN, CRG, CV from June 2016 • Coordination meetings with all groups from August 2016 (all groups will present their activities) • The unexpected issues were managed very well from the Groups • Some major outstanding items: • Impact of AUG tests on Cryogenics and following tests • Cryogenics lockout • The on site follow up for projects/changes which involves several groups, should be empowered LHC machine Schedule for YETS, INDICO 512656

  17. Coming events Next meeting – …… Time and Room TBC LHC machine Schedule for YETS, INDICO 512656

More Related