An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NDA Business Plan 2011 -2014 Nuclear Decommissioning Authority Dr Ian Hudson NDA Head of Programme Sellafield

  2. Introduction • Each year NDA produces a three year forward look business plan – latest 2011 – 2014 • Uses strategic direction to lay out key objectives and plans to deliver priorities • Reflects latest spending review – i.e. £1.5bn approx pa for Sellafield • Includes key activities and objectives for each site – i.e. Sellafield & LLWR

  3. Role of the Business Plan

  4. Budget provision 2% 3% 6% 2% 4% 26% 1% 7% 24% 1% 2% 13% 49% 60% 2005/06 - £2,188 m 2011/12 - £2,590 m Magnox LLWR Sellafield Ltd RSRL DSRL Springfields NDA HQ

  5. NDA, Sellafield Ltd & NMP

  6. Sellafield - contract structure • Maximum of 17 years – 5 + 5 + 5 + 2 • Secures breakpoints for formal review of progress and avoids complacency • Ability to re-compete (2 year process) if performance unsatisfactory • Efficiency Based Contract • Drives change programme & demands efficiencies • Sets clear targets and objectives • Change Programme • New performance plan, robust and underpinned • Soft and Hard aspects of performance • Safety culture • Attainment of fee driven by success in performance and continued efficiencies • More work than contract baseline • Same work at lower cost

  7. Business Plan priorities & targets Sellafield • 2011- 2014 Key Activities include completion of: • Active commissioning of SPRS • Construction of Evaporator D • Rang of enablers towards first retrievals in legacy plants • Targets 2011/12 include: • Magnox 800te decanned 434te av during previous 5 yrs • HAL containers 307 288 av during previous 5 yrs • THORP 419te sheared 149 te av during past 5 years • All to be reflected in Performance Plan reporting mechanism

  8. Business Plan priorities & targets LLWR • 2011- 2012 Key Activities include: • Decommissioning Plutonium Contaminated Materials (PCM) • Introduce new LLW packaging containers Construction of Evaporator D • Submit Esc to Environment Agency – complete • Segregated Waste & Disposal services • Work across NDA estate to implement national LLW strategy