From the Box to Packing in 30 minutes

From the Box to Packing in 30 minutes. Pack-in-a-Box components. Remove components and assemble bracket as shown Follow the instructions to pack your first column and learn how to use the system. Additional Equipment & Chemicals. ¼” wrench 5/8” wrench 7/16” wrench Phillips head screwdriver

holtz
Download Presentation

From the Box to Packing in 30 minutes

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. From the Box to Packing in 30 minutes

  2. Pack-in-a-Box components • Remove components and assemble bracket as shown • Follow the instructions to pack your first column and learn how to use the system

  3. Additional Equipment & Chemicals • ¼” wrench • 5/8” wrench • 7/16” wrench • Phillips head screwdriver • 30ml beaker • Waste container • Methanol • Chloroform • Spatula • Balance • Computer • Ultrasonic bath

  4. Column Packer Assembly • Pre assembled for supplied SSI column hardware.

  5. Mounting Packing Stand to Pump • Screw stand to side of pump using the two #6 screws provided.

  6. Plumbing the Pump Outlet to Packer Inlet Line

  7. Priming pumpsUse MeOH for this column • Open prime purge valve press prime button • With prime purge valve open use the supplied syringe to draw solvent through the pump • Prime pump • When pump is primed close the prime purge valve

  8. Packing Ring Seal Installation • Place ring in adapter as shown • Make sure ring is flat in bottom of adapter

  9. Packer Mounted to Stand • Mount packer to stand and tighten wing nuts • No wrenches are required to seal reservoir • Hand tighten end nuts

  10. Column Assembly • Assemble lower fitting of column and add frit to top end fitting and set aside to put on column after it is packed.

  11. System Assembled Correctly • The use of the Quick-Set software is not required but gives the most flexibility and will be used for this example

  12. Installing Quick Set • Insert Disk • Run the Quick-Set “setup.exe” program file & follow prompts. • Due to the many versions of Windows in use, your PC may have newer files than the ones being loaded. You will be prompted for a course of action, when in doubt, “keep” your existing files or “ignore” other messages. • Connect RS 232 Cable provided to the computer and pump • Turn on pump

  13. Click QuickSet • Go to Start/Programs • Click on Quick-Set • The screen below appears with the information on the program

  14. Automatic Set Up · Initial screen is for locating the SSI / LA pump ·  If communication does not initialize or if the pump is not on this list: Click on the “Poll Com Port For Device” button. · This will scan 9 possible PC COM ports for the attached device. · When the device is found, click on the” Continue” button.

  15. Getting To CP Screen Click on Constant Pressure

  16. Setting Flow and Pressure • Set to pressure limited ramp and click ‘send’ • Set upper pressure to 9999 psi; click ‘send’ • Set lower pressure to 0 psi; click ‘send’ • Set ramp speed to 100; click ‘send’ • Set max flow and pressure from table

  17. Adding Steps

  18. Packing program to load Send to pump

  19. Saving Your Packing Program • Click on “Save Settings” • Enter file name • Save save settings

  20. Mounting Column • Make sure packing ring seal is in adapter • Hand tighten column in adapter • Place plug in bottom of column • Remove plug just prior to starting pump

  21. Tighten Column on Packer • Use a ¼” wrench and 5/8” or adjustable wrench to snug column to packer • Do not over tighten ¼ turn past snug is fine • Fill column with 3 mL MeOH

  22. Setting up Graphing and Data Collection Click on Poll Flow and Pressure

  23. Saving Packing Data • Select Log data • Give file a name Click Log Data

  24. Making the Slurry • Weigh 3 gm of silica into 30 mL beaker • Add 20 ml of 50:50 Chloroform:Methanol (Straight MeOH can be used but is not as efficient) • Use a spatula to break up packing • Place in ultrasonic bath until uniformly dispersed • Pour in packing reservoir as soon as possible and pack column

  25. Adding Slurry • Use 20 mL of silica slurry and pour carefully into reservoir • Fill reservoir with washings of beaker and close

  26. Is It Closed? • Make sure the reservoir is full with slurry • Remove silica from threads • Hand tighten top nut

  27. Make Sure You Are Ready • Is the program loaded? • Is the pump primed? • Is there a waste collection vessel below the column? • Did you tighten the fittings? • Is there slurry in the reservoir and is the reservoir closed? • Are you set to graph the process and save your data? • If so, proceed

  28. Packing The Column • To run program, click on “Pump;” or if program is loaded click on “Start”

  29. Initial Packing Profile

  30. Running a Column Packing Profile

  31. Removing the Column • Stop the pump and let the pressure drop to 0 psi • Carefully unscrew the column, and using a flat spatula or razor blade, remove excess silica • Remove silica from threads if present • Place end fitting and frit on column and seal

  32. Removing Excess Silica • Work quickly with a spatula edge or razor blade

  33. Getting Ready to Pack Again • Pump remaining silica from precolumn for reuse or disposal • Empty reservoir • Install next column and repeat steps