An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Clean Air Project:Team Big Green SpaceGasmFinal Presentation Hillary Beltran, Edward Crawford, Nicole Harris, Edward Lowe, Emily Proano, and Kevin Wong December 2, 2010

  2. Mission Overview • Mission objective: Take measurements of the concentrations of carbon monoxide, carbon dioxide, and methane gases • Purpose of Mission: The team’s interest in the quality of air and changes that were recently experienced over the past few years • Hypothesis: Concentrations have increased during the course of the year

  3. Design Overview • Three Sensors: CO, CO2, and Methane • Arduinoand MicroSD Shield • Required Components • Camera, Hobo, Heater, and Batteries

  4. Functional Block Diagram

  5. Results and Analysis • microSD memory card failed to store data due to a simple error in code • Unable to compare predicted to actual data • Colorado Department of Public Health and Environment • Does not provide data on carbon dioxide and methane gases as initially expected • Team did not closely study what the department did or did not provide • Data provided for carbon monoxide is not significant • Online archived data dates to March 2008

  6. Results and Analysis • Team able to show expected increase in at least one gas: carbon dioxide • Shortfall: Readings taken from Mauna Loa Observatory in Hawaii

  7. Results and Analysis • HOBO temperature data:

  8. Images from Camera

  9. Flight Overview • Sensors were functional but could not store data on microSD memory card • Camera took images but memory card filled about halfway through the flight • HOBO successful took and stored internal and external temperatures and relative humidity • Heater system function (minimum internal temperature: -2.90°C) • Structure suffered minimal damages

  10. Failure Analysis • Not structural error • The structural suffered minimal damages • Internal components suffered no damages • Not electrical error • All the connections were present • Failure rooted in software

  11. /* Big Green SpaceGasm Java Code to be uploaded to Arduino */ //Add the SdFat Libraries #include <SdFat.h> #include <SdFatUtil.h> #include <ctype.h> //Create the variables to be used by SdFat Library Sd2Card card; SdVolume volume; SdFile root; SdFile file; char name[] = "BGSGfinaldata1.txt"; //Create an array that contains the name of our file. char contents[256]; //This will be a data buffer for writing contents to the file. char in_char=0; int index=0; //Index will keep track of our position within the contents buffer. String inin; intsensorValueCO = 0; intsensorValueCH = 0; int sensorValueCO2 = 0; String CO; String CH; String CO2; .... char name[] = "BGSGfinaldata1.txt"; Final Code Used on Launch Day =BAD Correct Code That Will Be Used Next Launch char name[] = "test1.txt";

  12. Conclusion • Data from external sources remain inconclusive • However, learned much from our failures • Now able to store the data that was recorded during flight • Find more reliable external source with which to compare our data • Re-flight in April 2011 highly anticipated and will yield conclusive data

  13. Appendix

  14. Lessons Learned • Carbon dioxide sensor short circuited due to too high of voltage/current • Camera should take images over longer time intervals • Conduct more system tests, namely for sensors and software • Ensure sensors taking data • Data being stored on microSD card and is retrievable

  15. Flight Readiness • Source of error has been traced to the code • Error was repeated with various tests done to affirm the source of error lay with code • Code rewritten and error solved • Structure does not need to be mended • For re-flight, new batteries with Velcro and a new CO2 sensor will be needed • Must be stored in dry, cool area

  16. Requirements Flow Down: Level 0

  17. Requirements Flow Down: Level 1

  18. Mass and Cost Summary

  19. Message to Next Semester • Course is challenging, but an invaluable and exciting learning experience • Communication, among others, is crucial • Subsystems can have own timetable • During full systems testing, each subsystem must be functional • If not, testing cannot continue until addressed • Time is not an ally • K.I.S.S. model – Keep It Simple Stupid • Given a measure of freedom • Remember constraints on costs, weight, and time