170 likes | 404 Views
North American Electric Reliability Council (NERC) . Transmission Reliability CriteriaWith no lines out, grid must remain stable with normal voltage and no loss of loadWith the loss of one line, grid must remain stable without overloading any other lines, and no additional loss of load other than
E N D
1. Meadow Brook to Loudoun 500kV Transmission Line A Review of the Need and Alternatives
A Dominion Analysis
November 2006
2. North American Electric Reliability Council (NERC) Transmission Reliability Criteria
With no lines out, grid must remain stable with normal voltage and no loss of load
With the loss of one line, grid must remain stable without overloading any other lines, and no additional loss of load other than the line that is out
With the loss of two or more lines, loss of load must be controlled without cascading outages
Compliance- Now Mandatory
Third party audits
Violations subject to fines up to $1M per day per event
3. Northeast Blackout - August 14, 2003(Map provided by Electric Transmission Week and ENERmap)
4. Northern Virginia: Growing Demand,Shortage of Generation
6. Past Network Transmission Work in Northern Virginia Year 2000
New transmission line - 230 kV Morrisville to Remington CT
Upgrade transmission line - 230 kV line 2086 Remington CT to Warrenton
Year 2001
New transmission line - 230 kV Ladysmith to Ladysmith CT
Year 2002
New transmission line - 230 kV Clifton to Reston
Upgrade transmission lines - 115 kV lines 145 & 183 Remington to Possum Point
Year 2003
New transmission transformers - Possum Point and Pleasant View 500-230 kV transformers
Upgrade transmission lines - 230 kV lines 225, 2074 & 2088 North Anna to Gordonsville
Year 2004
Upgrade transmission lines - 230 kV lines 2039 & 2040 Morrisville to Marsh Run
Year 2005
New transmission line and station - 230 kV Beaumeade to Greenway & Greenway substation
Upgrade transmission station - 230 kV ring bus Beaumeade substation
7. Other Network Transmission Work in Northern Virginia Year 2006
New transmission transformer - Clifton 2nd 500-230 kV transformer
Upgrade transmission line - 500 kV line 551 Mt Storm- Doubs
New transmission voltage support - 6 transmission capacitor banks
Year 2007
New transmission line and substation - 500 kV Morrisville to Bristers & Bristers substation
Upgrade transmission line - 230 kV line 2063 Clifton to Ox
Year 2008
New transmission line - 230 kV Brambleton to Greenway
Upgrade transmission lines - 230 kV lines 2045 & 2094 Loudoun to Brambleton
Upgrade transmission line - 230 kV line 251 Idylwood to Arlington
Year 2009
New transmission line and transformer - 230 kV Bristers to Gainesville & 500-230 kV transformer at Bristers
New transmission transformer - Possum Point 2nd 230-115 kV transformer
Year 2010
Upgrade transmission line - 230 kV line 2097 Ox to Idylwood
17. Demand -Side Management Program Time-of-Usage Metering
Time-of-Usage (TOU) meters provide price incentives to reduce electric consumption during peak times
Load Curtailment Rates
Lower rates for customers who agree to have their load curtailed for a fixed number of days each year
Demand Response Program
Direct customer payments for reducing electric consumption when either wholesale prices are high or the reliability of the electric grid is in jeopardy
18. Summary and Conclusion The risk of a blackout will exist in Northern Virginia unless action is taken by 2011
The 502 Junction-to-Mt Storm-to-Loudoun line resolves all overloads in the Northern Virginia area, as well as the broader region
Other alternatives fail to resolve the overloads in either Northern Virginia or the region
The 502 Junction-to-Mt Storm-to-Loudoun line is the best solution to minimize the risk of a blackout in Northern Virginia