1 / 17

Meadow Brook to Loudoun 500kV Transmission Line

North American Electric Reliability Council (NERC) . Transmission Reliability CriteriaWith no lines out, grid must remain stable with normal voltage and no loss of loadWith the loss of one line, grid must remain stable without overloading any other lines, and no additional loss of load other than

ike
Download Presentation

Meadow Brook to Loudoun 500kV Transmission Line

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


    1. Meadow Brook to Loudoun 500kV Transmission Line A Review of the Need and Alternatives A Dominion Analysis November 2006

    2. North American Electric Reliability Council (NERC) Transmission Reliability Criteria With no lines out, grid must remain stable with normal voltage and no loss of load With the loss of one line, grid must remain stable without overloading any other lines, and no additional loss of load other than the line that is out With the loss of two or more lines, loss of load must be controlled without cascading outages Compliance- Now Mandatory Third party audits Violations subject to fines up to $1M per day per event

    3. Northeast Blackout - August 14, 2003 (Map provided by Electric Transmission Week and ENERmap)

    4. Northern Virginia: Growing Demand, Shortage of Generation

    6. Past Network Transmission Work in Northern Virginia Year 2000 New transmission line - 230 kV Morrisville to Remington CT Upgrade transmission line - 230 kV line 2086 Remington CT to Warrenton Year 2001 New transmission line - 230 kV Ladysmith to Ladysmith CT Year 2002 New transmission line - 230 kV Clifton to Reston Upgrade transmission lines - 115 kV lines 145 & 183 Remington to Possum Point Year 2003 New transmission transformers - Possum Point and Pleasant View 500-230 kV transformers Upgrade transmission lines - 230 kV lines 225, 2074 & 2088 North Anna to Gordonsville Year 2004 Upgrade transmission lines - 230 kV lines 2039 & 2040 Morrisville to Marsh Run Year 2005 New transmission line and station - 230 kV Beaumeade to Greenway & Greenway substation Upgrade transmission station - 230 kV ring bus Beaumeade substation

    7. Other Network Transmission Work in Northern Virginia Year 2006 New transmission transformer - Clifton 2nd 500-230 kV transformer Upgrade transmission line - 500 kV line 551 Mt Storm- Doubs New transmission voltage support - 6 transmission capacitor banks Year 2007 New transmission line and substation - 500 kV Morrisville to Bristers & Bristers substation Upgrade transmission line - 230 kV line 2063 Clifton to Ox Year 2008 New transmission line - 230 kV Brambleton to Greenway Upgrade transmission lines - 230 kV lines 2045 & 2094 Loudoun to Brambleton Upgrade transmission line - 230 kV line 251 Idylwood to Arlington Year 2009 New transmission line and transformer - 230 kV Bristers to Gainesville & 500-230 kV transformer at Bristers New transmission transformer - Possum Point 2nd 230-115 kV transformer Year 2010 Upgrade transmission line - 230 kV line 2097 Ox to Idylwood

    17. Demand -Side Management Program Time-of-Usage Metering Time-of-Usage (TOU) meters provide price incentives to reduce electric consumption during peak times Load Curtailment Rates Lower rates for customers who agree to have their load curtailed for a fixed number of days each year Demand Response Program Direct customer payments for reducing electric consumption when either wholesale prices are high or the reliability of the electric grid is in jeopardy

    18. Summary and Conclusion The risk of a blackout will exist in Northern Virginia unless action is taken by 2011 The 502 Junction-to-Mt Storm-to-Loudoun line resolves all overloads in the Northern Virginia area, as well as the broader region Other alternatives fail to resolve the overloads in either Northern Virginia or the region The 502 Junction-to-Mt Storm-to-Loudoun line is the best solution to minimize the risk of a blackout in Northern Virginia

More Related