Maryland Avenue and Arkwright Street. Jerry Auge, PE Project Manager Ramsey County 651-266-7117 jerry.auge@co.ramsey.mn.us April 2, 2013. Presentation Topics. Purpose/Background of Project Proposed Improvements Project Limits Infiltration Property Acquisition Update Costs Schedule
E N D
Maryland Avenue andArkwright Street Jerry Auge, PE Project Manager Ramsey County 651-266-7117 jerry.auge@co.ramsey.mn.us April 2, 2013
Presentation Topics • Purpose/Background of Project • Proposed Improvements • Project Limits • Infiltration • Property Acquisition Update • Costs • Schedule • HSIP Crash Data
Project Purpose • Improve Safety within the Corridor • Adding Left Turn Lanes on Maryland Avenue • Estimated Accident Reduction of 58%*** • Increase Lane Width to 11 feet • Improve Radii at Intersection of Arkwright St. • Consolidate Driveway Access near Arkwright St. • Improve Pedestrian Facilities at Intersection
Maryland Ave/Arkwright Intersection • #1 Rated County Road intersection for Accidents in St. Paul • Rated #4 • Intersection of Highest Accidents @ 175 crashes • Crash Data for June 2007-2012 • ~35 crashes per year
Existing Maryland Ave at Arkwright St. • Roadway width 40 feet • Four lane section • Lane width 10 ft • No designated left turn lanes at Arkwright St. • 30 mph
Proposed Maryland Ave at Arkwright St. • Roadway width 44 feet • Four lane roadway • 2 foot curb and gutter • 11’ left turn lane • 11’ thru lanes • 5’ sidewalk • 5’ boulevard • 30 mph
Water Quality Improvements • Watershed requires Improvements • Infiltration/Water Quality Improvements • Necessary for the Proposed Project Imp. • Proposing to install within the Southwest Corner of Westminster/Maryland.
Parcels within the Project Limits • Total of 31 Parcels • 4 Commercial Properties • 26 Residential Properties • 1 MnDOT Property
Property Acquisition Update • Total of 31 Parcels • 1 Property has Settled • 15 Properties Tentatively Settled • 15 Properties Unsettled
North East Quadrant • 3 Residential Properties • Commercial Property • County/City has Prepared for all Options for Northeast Quadrant • St. Paul Water/Sewer Division • Other Private Utilities
Project Costs • Federal Funding $1,363,300 • County State Aid Funding $1,350,000 • City Funding $1,050,000 • Total Project Costs $3,963,300
Project Schedule Acquire All PropertiesMay 20, 2013 Project Approvals May 2013 Advertise Project June 2013 Utility Relocations July 2013 Start Construction August 2013 End Construction October 2013
Project Phasing • To be Determined • Private/Public Utility Work • Community Input • Project Duration • Future Open House Meeting (April/May)
Crash Data • Report Prepared by FHWA (Crash Reduction Factors) • Iowa State and Iowa Department of Transportation Study (Effectiveness of Roadway Safety Improvements) • FHWA – Tool Box of Counter Measures
Data In Reports • Estimated Crash Reduction to be Expected • Provide 12 Tables (FHWA)grouped as: • Intersections • Roadways • Non Intersection Crashes • Pedestrian Crashes • Tables provide a compiled Crash Reduction Factor (CRF)
Maryland Avenue at Arkwright Street(Intersection) • CRF Incorporate this Information: • Crash Type • Crash Severity • Area Type • Configuration • Control • Major Traffic Volumes • Study Type • Minor Traffic Volumes • Reference • Intersections Observed • Crash Reduction Factor • Standard Error • Range
Maryland Avenue andArkwright Street Jerry Auge, PE Project Manager Ramsey County 651-266-7117 jerry.auge@co.ramsey.mn.us April 2, 2013