1 / 16

Maryland Avenue and Arkwright Street

Maryland Avenue and Arkwright Street. Nick Fischer, EIT Ramsey County 651-266-7119 nicklaus.fischer@co.ramsey.mn.us Jerry Auge, PE Project Manager Ramsey County 651-266-7117 jerry.auge@co.ramsey.mn.us April 29, 2013. Maryland Ave Reconstruction. Presentation Topics. Project Outline

Download Presentation

Maryland Avenue and Arkwright Street

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Maryland Avenue andArkwright Street Nick Fischer, EIT Ramsey County 651-266-7119 nicklaus.fischer@co.ramsey.mn.us Jerry Auge, PE Project Manager Ramsey County 651-266-7117 jerry.auge@co.ramsey.mn.us April 29, 2013

  2. Maryland Ave Reconstruction

  3. Presentation Topics • Project Outline • Proposed Improvements • Construction Phasing • Project Cost • Acquisition Update • Schedule

  4. Purposed Improvements • Improve Safety within the Corridor • Adding Left Turn Lanes on Maryland Avenue • Increase Lane Width to 11 feet • Improve Radii at Intersection of Arkwright St. • Consolidate Driveway Access near Arkwright St. • Improve Pedestrian Facilities at Intersection

  5. Existing Maryland Ave at Arkwright St. • Roadway width 40 feet • Four lane section • Lane width 10 ft • No designated left turn lanes at Arkwright St. • 30 mph

  6. Proposed Maryland Ave at Arkwright St. • Roadway width 44 feet • Four lane roadway • 2 foot curb and gutter • 11’ left turn lane • 11’ thru lanes • 5’ sidewalk • 5’ boulevard • 30 mph

  7. Manhole Reconstructs & Gas Main Abandoned Gas Main

  8. Project Phasing Road Open to Traffic Two Way Traffic One Way Traffic Longer Construction Schedule Road Closed in Phases 3 Phases Shorter Construction Schedule

  9. Project Phasing Build Under Traffic One Way Traffic Expensive Traffic Control Temporary Signal Back In Trucks Temporary Roadway Temporary Closures Utilities 5 weeks per side ( 10 weeks total) Road elevation change Extra construction cost $100,000

  10. Project Phasing Road Closure • Better Roadway Construction • Shorter Construction Time • Remove Gas Main • No Temporary Signal • Raising Intersection • Reconstruct Manholes • Bus Route Move to Clark St • 3 wks, 3wks, 1 wk • 7 weeks total

  11. Phase 3 Intersection Closure Phase 1 Closure Phase 2 Closure

  12. Maryland Ave Detour Intersection Closed Closed Closed

  13. Project Costs • Federal Funding $1,363,300 • County State Aid Funding $1,350,000 • City Funding $1,050,000 • Total Project Costs $3,963,300

  14. Property Acquisition Update • Total of 31 Parcels • 26 Property has Settled • 1 Properties Tentatively Settled • 4 Properties Unsettled

  15. Project Schedule ROW acquired May 20, 2013 Project Approvals May 2013 Advertise Project June 2013 Utility Relocations July 2013 Start Construction August 2013 End Construction October 2013