LCLS Cavity BPM Production Status

LCLS Cavity BPM Production Status. M1-Tool Works BPM Production. M1 awarded contract for machining bodies and transitions for 20 sets of parts First Production BPM mechanical measured and Pre-lim cold test look very good. First production unit. Cavity Production Status.

iniko
Download Presentation

LCLS Cavity BPM Production Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LCLS Cavity BPM Production Status

  2. M1-Tool Works BPM Production • M1 awarded contract for machining bodies and transitions for 20 sets of parts • First Production BPM mechanical measured and Pre-lim cold test look very good

  3. First production unit

  4. Cavity Production Status • M1-Tool Works to deliver 11 units 1/22/08 presently on schedule • Exercised the option for additional 20 units order from M1-Tool 1/08 • Parts are on time and in spec so far

  5. Cold Test Set-Up for Pre-Braze test • New production test fixtures for pre-braze testing • First production unit looks good and parts are at Altair waiting to be brazed

  6. Cavity BPM Cold Test Data

  7. First Production Unit Shipped to • Serial # 010 shipped to Altair for brazing 12/21/07 • Unit pending complete braze due to window problem

  8. Production Risks (Presented at FAC 10/30/07) • New End Cap design • New tuning scheme • Window plating problem • Unexpected integration problem • Unexpected vendor problem

  9. The Window Braze Yield Problem • Problem brazing the window into the transition has caused delivery delay • Convergence and down-select of possible solutions pending • Concentration of effort critical

  10. Understanding the Problem • History • Why were ALL the soldered units vacuum tight? 15 for 15 • Why did the units built for the 3-BPM work so well compared to present results 6 small leaks, 9 good NO CRACKING

  11. BPM Window Braze History • Prototype cold test unit, ITS test unit and 3-BPM test unit S/N 01 soldered Sn-Ag-Cu Vacuum tight • 2 test brazes Georo Vacuum tight • 3-BPM S/N R/0 first Georo braze Vacuum tight

  12. Georo Test Braze before 3-BPM units • First test brazes clean and vacuum tight 5/12/07 • No risk at this time so units for 3-BPM testing would be processed with Georo braze material

  13. First Problem Window • 3-BPM test Ser # 03 Georo Braze Results: • 2 out of 5 leaked and the 2 that leaked had “glossy” Ni plating • 3-BPM test Ser # 02 Georo Braze Results: • 4 out of 5 leaked and the 4 that leaked had “glossy” Ni plating

  14. Corrective Action from 3-BPM Window Failures • Start R&D program to identify problem with bright Ni • CPI suggested using gold plating of first trials • First sample failed 10/07 because of apparent cracks and “spattering” • Possible cause was cool down too rapid

  15. Window Problem Status 01/21/08 • Moly retaining ring and retaining outer block • Lower temperature braze (Orotin) with induction heating re-work • CPI supplies transition with window installed • Kovar frame • Two piece transition • Bolt on window • Coax adapter

  16. Cavity BPM Production Recovery Options without changing the design • Option 1 Lower temperature braze (Orotin) and Induction heating re-work plan • Option 2 Work with CPI for a turn-key solution providing completed transition • Option 3 Braze window into a frame (Kovar) with similar expansion coef and weld into transition

  17. CONs Yield not satisfactory Re-work plan needs work Braze with existing/modified parts • PROs • Lowest risk option • Fastest recovery • Re-work plan possible • Lowest cost impact • No risk to qualified BPM system design

  18. Induction Heating • Working with Ameritherm to re-work window after failed braze • Braze can be re-worked by applying additional paste or powder to joint

  19. Receiver Electronics Production Status • All parts on order • Test fixtures developed • Parts to start arriving 2/08

  20. Production Status • M1-tool Works delivered first unit 11/07 on time and in spec • First unit has been QA tested and cold tested with very good results • First unit is at Altair being Brazed less waveguide transitions • ANL to supply Altair with first set of modified window/transitions • Addition 11 BPMs in process at ANL

  21. Production Milestones • Production of 1 BPMs for LTU 02/08 • Production of 11 BPMs for undulator/LTU 03/08 • Production of 12 BPMs for undulator 04/08 • Production of 12 BPMs for undulator 05/08 • Spares 4 BPMs 06/08 • 40 sets of Electronics 08/08