Zoran AKA Zscaler Project AKA Project Scrubber Project Update Pack 1

Zoran AKA Zscaler Project AKA Project Scrubber Project Update Pack 1. Index: Zscaler Project Detailed Requirements Solution AU & NZ Solution Global Scope, Constraints & Assumptions Deployment Timeline Noteworthy points Appendix 1: Rule sets to be enforced

isaiah
Download Presentation

Zoran AKA Zscaler Project AKA Project Scrubber Project Update Pack 1

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Zoran AKA Zscaler ProjectAKA Project ScrubberProject Update Pack 1 Index: • ZscalerProject • Detailed Requirements • Solution AU & NZ • Solution Global • Scope, Constraints & Assumptions • Deployment Timeline • Noteworthy points • Appendix 1: Rule sets to be enforced • Appendix 2: Policy Exclusion Process Zoran Island, Phuket, Thailand

  2. ZscalerProject Mission Statement Establish a common web filtering and monitoring platform High Level Requirements • Clientless • Centrally ‘located’ • De-Centralised Manageable • Reduction in IS managed infrastructure • Common rule set

  3. Detailed Requirements

  4. Detailed Requirements (cont’d)

  5. Solution AU & NZ (logical flow) • Client configured to Auto detect Proxy setting\ • Central PAC (WPAD) file directs traffic to trusted sites to Squid Proxy • All other traffic to zScaler where user will be authenticated (login or cookie)

  6. Solution Global (logical flow) • Central PAC (WPAD) file directs all traffic to zScaler(gateway.zscaler.net:80) • No user authentication

  7. Scope, Constraints & Assumptions • Scope; • IE browser • PC and Laptops on Windows OS only • Enforcement and or traceability of adherence to Group Web Usage Policy • Starting with a ‘clean slate’ by not bringing across hundreds of ‘old’ and undocumented rules • Universal PAC (WPAD) file for all regions • Deployment limited to AU, NZ, UK, US and HK • Constraints; • Resource availability • Users without email address can not access non trusted sites (AU & NZ only)

  8. Scope, Constraints & Assumptions cont’d • Assumptions; • Trusted sites list to be defined ‘out side’ of Project • Internal resources are available as scheduled • Minimal calls to Service Desk • ‘Regional’ Assumptions; • Australia & NZ • All Desktops are MOEd and will accept Group Policies • All users arein AD • User have email addresses (for access to ‘non trusted’ sites) • Global • All PCs will accept Group Policies • Root certificates (HTTPS) can be deployed to desktops • All Desktops are on IE7 or above

  9. Deployment Timeline Highlights • Melbourne HO will be on Zscaler by 27/8 • Australia by 9/9 • NZ by 13/9 • Global by October (TBC) *Timing for Global deployment is indicative and subject to confirmation with and acceptance by regional IS and Business

  10. Noteworthy points • Plan has been developed with the assistance of and agreed to the IS team • Melbourne HO on line with Zscaler by 27/8 is achievable • AU and NZ online with Zscaler by 13/9 is achievable • Global deployment by October is feasible but subject to further planning and agreement • PAC file is universal and same version (multiple instances) of file will be used by ALL regions • PAC file is modular, documented and readily configurable should the need arise • PAC file will be accessed as a WPAD and defined via DNS • Proxy settings will be deployed via Group Policy • As AD.Internal is rolled out PAC file will be centralised and regional instances removed

  11. Appendix 1:Rule sets to be enforced • Adult Material • Drugs • Gambling • Violence • Weapons/Bombs • Tasteless • Militancy/Hate and Extremism • Illegal or Questionable • Games • Internet Communication • Peer to Peer Site • Security • Society and Lifestyle • Social Networking (i.e. Facebook etc.)

  12. Appendix 2:Policy Exclusion Process