An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MINOS NEAR DETECTOR • Status • Plans for Installation and Commissioning P. Shanahan FNAL AlExp 11/17/03

  2. MINOS Detectors • 1” Fe/1cm plastic scintillator • 4.1 cm transverse segmentation • WLS fiber readout into multi-anode PMTs Near Detector readout single ended

  3. Near Detector • Smaller than Far Detector • 282 planes (153 scintillator), partial instrumentation • 980t, 4.8m x 3.8m x 16.6m • 1.2T magnetic field Every 5th plane throughout detector is fully instrumented

  4. Near Detector Function First 120 planes: each plane instrumented Last 162 planes: multiplexed spectrometer region cm Target region MC Spectrometer Region:4x multiplexing, 4/5 planes not instrumented Veto region Calorimeter region cm cm cm

  5. Readout Electronics Front End Mother Boards (MINDERs) • High Rate Neutrino Experiment • >30 interactions/10ms spill • QIE based system • Multiranging, Deadtimeless 19ns sampling over entire spill • Electronics Assembly nearly complete • Checkout >50% complete MINDER Crate QIE Daughter Board(MENU) Trigger/Keeper Readout Crate Readout Boards (MASTER) Component Count (not counting ~10% spares): 9328 MENUS 583 MINDERS 81 MASTERS

  6. Near Detector Status • All ND planes ready for installation • Staging at New Muon • Rack assembly in progress • Beneficial Occupancy: Jan. 31, 2004 • Integration tests: 8 spectrometer planes • Prior to B.O., test integration of planes, fiber cables, PMTs, electronics, Light Injection • Possibly readout with DAQ, schedule permitting

  7. Installation • Installation expected to start ~ 6-8 weeks after Beneficial Occupancy • Aim for 2 planes/day • Stage from NMS to MINOS Surface Building • Expect O(30) weeks to complete Practicing plane manipulation with strongback

  8. Commissioning • Aim to commission planes as they go in • Light leaks • basic functioning, operational parameters of scintillator, PMT, electronics, Light Injection system • Great experience gained at Calibration Detector at CERN • Hope to demonstrate interactions in 1st few minutes of neutrino beam.