1 / 14

MINOS Far Detector Installation & Commissioning

MINOS Far Detector Installation & Commissioning. Jeff Nelson MNHEP DoE Visit September, 2002. Outline. Plane assembly Status & experience Projection methodology Projected schedule Issues & costs Safety Detector operation Live time & data collected. The detector in August….

myrna
Download Presentation

MINOS Far Detector Installation & Commissioning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MINOS Far Detector Installation & Commissioning Jeff Nelson MNHEP DoE Visit September, 2002

  2. Outline • Plane assembly • Status & experience • Projection methodology • Projected schedule • Issues & costs • Safety • Detector operation • Live time & data collected

  3. The detector in August…

  4. Assembly & Commissioning • SM1 Completed in July • Met commissioning milestone on July 26th • 354 of 484 planes installed • 73% completed, 3.9 kton • 348 planes commissioned • All commissioned planes are collecting calibration & cosmic ray data

  5. Installation Schedule • We have averaged 6.2 planes per week since installation reached full efficiency in Nov. 01 • Currently 4 days behind working schedule • Amall drop off in rate associated with a few factors including • Workers now have vacation time • Some attrition in staffing • Plots shows • Current FNAL working schedule • Actual installation schedule • Projected completion schedule • Differences described in following slides

  6. Installation Extrapolation Data • History of MINOS installation hours & plane installation in 2 week periods • Some drop in hours work due to crew having accumulated vacation in their first year of employment • About a 10% effect • Fit shows what a worker accounts for roughly 0.25 planes/week • No drop off in efficiency for reasonable staffing levels • Some expected a levels below 14 FTE

  7. Staff & Future Projections • Job Market in northern Minnesota • Down turn in iron mining in early 2001 • We were able to hire some very experienced millwrights & operators for the installation crew • Steel mills are hiring again • We have lost one staff per month each of the last 4 months • We are starting to replace these workers to maintain the current efficiency • The projections show what happened if we replace one of the current losses & all further losses • This is our current plan • Adding new crew has safety, quality & efficiency implications during training period • Particularly an issue for materials handling • Costs are about $1k per new employee • We do not take this lightly

  8. Costs & Schedule Implications • The amount of work is the same and there are no changes in efficiency • There are no significant costs for WBS 2.4 associated with install schedule adjustments • The only cost implications are to on-project operations costs • 2nd shift charges for DNR hoistman and on-call electricians • Physicist shift leader travel • Staffing for receiving at surface building • All 3 amounts to $5k per week of slip • Now projecting a 6 week change in completion date

  9. Safety at Soudan • Major activities • Continued monthly & annual outside inspections of equipment and facilities • Materials handling procedure review • Field mapping, signage, & training • Monthly joint safety meetings continued throughout the period • Back safety • Annual fire safety refresher • Annual operators certification • Cryogenic safety • Site safety update • Rescue team exercises

  10. Safety at Soudan • We have had 4 safety reports at Soudan since the last review • 1 lost days incident • Most serious was a herniated disk while moving steel plates at the assembly workstation • 5 safety reports • 3 near misses • 2 no list time accident • Incident rates for project • A reportable incidence rate of 3.1 @ (per 200,000 hours worked, for crew + physicist) • A lost time incidence rate of 2.5 @ • A lost days incidence rate of 0.5 @

  11. Detector operations • Since the summer we have been collecting data for calibration and cosmic rays • We have also been working to increase the live time • Addressing potential hardware impediments • HV monitoring improved and hardware swaps • Optimizing automatic recovery hardware/software • Have made good progress since early spring in increasing live time

  12. Slides in Hand

  13. Physicists & Installation Monthly averages • A total of 900 physicist weeks or 18 physicist years at Soudan on installation tasks • No safety incidents involving physicists at Soudan! Today

  14. Laboratory Staff Organization

More Related