Near Detector Electronics Status. Status Production Issues. Peter Shanahan FNAL MINOS Collaboration Meeting June 13, 2003. Near Detector Electronics. MINDER modules. MINDER Crate. MASTER Module. Trigger/Keeper. Component Count (not counting ~10% spares): 9328 MENUS 583 MINDERS

kalia-neal
Download Presentation

Near Detector Electronics Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Near Detector Electronics Status Status Production Issues Peter Shanahan FNAL MINOS Collaboration Meeting June 13, 2003

  2. Near Detector Electronics MINDER modules MINDER Crate MASTER Module Trigger/Keeper Component Count (not counting ~10% spares): 9328 MENUS 583 MINDERS 81 MASTERS MASTER Crate

  3. Near Detector Electronics Status • Schedule Status (BCWP/Total Budget): • 88% (April 03) • All WBS 2.3.1 system components are in production • Problems with MENU startup • All Printed Circuit boards in Assembly phase (or done…) • Thorough checkout in progress • All power supplies received/ crates in progress • WBS 2.3.6 • Auxillary systems (timing) • Minder Timing Modules, Clock Fanouts, Master Clock Controller done • Redesign of VME Timing Module for flexibility

  4. MENU Production • Front-end daughter card • Supports and reads out QIE • Stores digital data in pipeline • 9328 in system • 1440 plus spares required for CALDET

  5. MENU Production Problems • Sporadic production startup: • Fabrication • Solder on gold contacts – not noticed until fabrication began. • Vendor has accepted responsibility: inspection+new boards • Vendor inspection insufficient (no microscope on QC line!) • Assembly • Incorrect 1st articles • Overheated “burn-in” by vendor on 200 boards • Poorly tuned initial automated optical inspection by vendor • Wrong solder flux on several hundred boards • All problems addressed by vendor • Production has finally reached steady rate with consistent quality • Much effort on 14th floor: Lou Dal Monte, Merle Watson, Charlie Nelson

  6. MENU Good News • 5000 boards in hand • Checkout rate of boards with no acute problems is >90% • Assumed 67% in checkout schedule • Thorough checkout of all MENU functionality • IIT Undergrads for Checkout • Resident at FNAL for 5 weeks • Will later take test-stand to IIT • Very helpful in meeting CALDET schedule • Long-term production • Rate of 330/wk will complete production by 12/31/03

  7. Argonne Checkout • MINDERS, MASTERS, KEEPERS • Minders loaded with MENUs • Full system tests • Dave Reyna: Pedestals, DC Calibration • Tests virtually all aspects of the entire system • Lower Level Testing • Gary Drake, Bill Haberichter, Tim Cundiff, et al. • Testing all bits, reading/writing all registers, etc • Checkout done with a few sets of PROMs • Final PROMs will be burned post-CALDET • Shipping for CALDET in progress

  8. 2003 CALDET Run • Sept. 4 – Oct. 4, 2003 • 1440 channels on Near Detector Electronics • Full instrumentation of 1 side (actual ND is one sided) • Near only, and Near/Far running • Production calibration of Near response • ND Electronics is principle focus of run • Ship electronics in late June • L3 milestone 7/7/03 • Move to beam enclosure 8/18/03

  9. Near Detector Electronics Status All modules have CALDET quantities met Spares (~10%) not included in this table. Various Auxillary cards not included

  10. Summary • Near Electronics Production is Well Underway • All boards in assembly (or done!) • CALDET quantities are met • Thorough Checkout in progress at Argonne, FNAL • IIT help on MENU checkout • Production appears well on schedule for detector installation