EMCal work@Grenoble

EMCal work@Grenoble. For 7/11 EMCal Supermodules (3 done) Led test of delivered stripmodules (from Catania, Frascati, Nantes, WSU) Assembly (inserting stripmodules in SM crate) Cabling (US and EU SM signal cables are done @Grenoble) Calibration (Muons cosmic test bench) Crating

jacie
Download Presentation

EMCal work@Grenoble

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EMCal work@Grenoble • For 7/11 EMCal Supermodules (3 done) • Led test of delivered stripmodules (from Catania, Frascati, Nantes, WSU) • Assembly (inserting stripmodules in SM crate) • Cabling (US and EU SM signal cables are done @Grenoble) • Calibration (Muons cosmic test bench) • Crating • Shipping and Customs to CERN • Design and production of the STU card • Production of all EU Strap foils (3 SM)

  2. Infrastructure @Grenoble 220 m² assembly building dedicated to the EMCal project -> DCal Project 4 SM can be stored (more if new platforms are made)

  3. Assembly tools All needed tools are operationnal and can be re-used for DCal SM Strip Handling Tool 4 SM Platforms

  4. Cosmic test bench

  5. Cosmic test bench 2 SM can be sitted side by side for combined Assembly / Calibration

  6. Crating & Shipping Procedure for: Loading at Grenoble, shipping, customs, unloading at CERN are validated and can be re-used for DCal SM

  7. Schedule Assembly, test and calibration for 1 SM: (based on 3 SM experience) • (under the hypothesis that the stripmodule are fully equipped (LED, APD etc …) • Strip delivery + first LED test (standalone) :  3 days (1 day / 1/3) • Cabling : 3 days (1 day / 1/3) • LED driver system + fiber assembly : 1 day • Electronics assembly and test : ~ 3 days • Calibration measurement : • 3 passes / 1/3rd 9 days 4 weeks minimum are required to assemble and calibrate a full Supermodule • Manpower (FTE): 1 Eng. + 2 Tech. + 4 physicists

  8. Grenoble possible contribution to D-Cal • Assembly, cabling, calibration and shipping of DCal SModules • Management of all DCal SM cables production at Grenoble. • Production of strap foils for 2 (or more) DCal SM. • If green light from IN2P3. • If no impact on EMCal schedule. • If manpower support from D-Cal contributors. (SM Calibration) • More platforms must be produced to store EMCal-DCal SM @ Grenoble

  9. Cosmics calibration Test and calibration : • Fix any hardware problems (LED, ADPs, cabling, electronics …) • Adjust the APD gain on the overall SM • Calibration performed by 1/3rd of SM • 3 passes required to achieve < 3% dispersion (starting from 15%). • 16 hours/pass (200 to 500 muons / tower required ~15% ~2.3%