Tailings Dam Safety And Implementation Of Safety Guidelines By A Tailings Dam Operator. Why are Dam Safety Programs Important?. Los Frailes Spain - 1998. Merriespruit South Africa - 1994. Dam Safety Program Implementation. Guidelines provide templates and flow sheets for dam safety programs
E N D
Tailings Dam Safety And Implementation Of Safety Guidelines By A Tailings Dam Operator
Why are Dam Safety Programs Important? Los Frailes Spain - 1998 Merriespruit South Africa - 1994
Dam Safety Program Implementation • Guidelines provide templates and flow sheets for dam safety programs • Operator must translate these into activities that can be carried out at the tailings management site to create an effective dam safety program
Dam Safety Program Development • A good Dam Safety Program requires collaboration of a number of groups. • Operators, designers and regulators must all provide input to the dam safety program • Risk based approach can simplify the dam safety program: • Consider consequences of potential failure modes • Focus program on key failure modes • Program must consider the “tailings management system” – not just the dam • Program must be set up understanding that the system and risks will change over the mine life – recognize the changing conditions and changing risk
Roles and Responsibilities • Roles and responsibilities must be clearly defined • The designer and the regulator do not control the operation of the facility and are not involved in the day to day operation • Therefore, everyone must understand that the owner/operator is ultimately responsible for the safe operation of the facility • The Mine Manager must accept this responsibility and mandate that the dam safety program will be followed without exception.
Training • Best to have designer involved in training • Present key aspects of the design, critical issues. Helps to focus site staff on the key issues • Designer to have at least annual review of performance – field inspection and review of documentation • All personnel that will be in vicinity of facility should be trained to identify conditions that could lead to failure • All personnel should know how to report a potential problem
Inspections • Frequency of inspections and monitoring data collection depends on the rate of system changes • Routine inspections on a weekly or monthly basis • Frequency may change depending on the season • Daily to weekly during wet season or during snow melt • Monthly during dry season • By site personnel • Engineering inspections on a semi-annual to annual basis • By designer • Special inspections after significant events • By designer and site personnel following earthquakes and floods • A dam safety review every 5 to 10 years • By independent engineer (not the designer)
Inspections • Check lists for inspections • Don’t miss key information • Simplifies inspections – inspector can focus on the observations • Inspection forms • Information is presented in a consistent format, changes in system performance are more easily identified. • Completing the checklist does not mean the inspection is complete • Evaluation of the information collected is the important step – how is the performance of the facility changing and are these changes consistent with the expected performance
July 2005 June 2006 Inspection Forms to Include Photographs PHOTOGRAPH North Dam 1: View to the east along the downstream toe of the North Dam near the west abutment. Toe and face are in good condition. Small puddles of water in natural topographic depressions. Condition in 2006, including the size and location of water downstream of the dam, is similar to that observed in 2005 as shown by comparison of the photographs.
Graphical Presentation of Monitoring Data Aids Interpretation
Key Learnings • Training • Everyone involved with the tailings and water management facility should be trained to identify and report conditions that could lead to failure. • Training workshops involving the designer, the operators and the regulators are very effective. The operators need to understand what is important for dam safety, and why it is important.
Key Learnings • Inspections and Data Collection • Continuity of personnel important • Human eye can identify small or subtle changes in a structure • Filling out the inspection form is only the first step. The inspection is not complete until the interpretation of performance is complete. • There is a learning curve to understanding the performance of a dam
Key Learnings • Review and analysis • Continuity of personnel important • There is a learning curve to understanding the performance of a dam • Important to have independent review and verification of the dam safety periodically • Responsibility • The Mine or General Manager has the largest influence on successful implementation of a dam safety program. Dam safety must rank equally with production.
General Comments • Visit mines with similar types of tailings management systems • Discuss the dam safety program • Discuss the good and bad parts of your program so that both can learn • Review case histories of dam failures • Modern dam failures are well documented and the root cause of the failure is often identified in the investigation reports. • Obtain current copies of dam safety guidelines • Guidelines are updated as the understanding of the mechanisms of dam failures improves • With modern communication systems, news of a tailings facility failure is known worldwide immediately and will affect the international mining community
Our goal: our tailings dams become an integral part of the environment post-closure
Feedback on the UNECE guidelines • This document is a good starting point but to be useful to industry (dam operators) guidelines need to be specific • There are a number of useful groups of documents already in use – such as the CDA Dam Safety Guidelines combined with the Mining Association of Canada guidelines for designing a tailings facility and for preparing operation, maintenance and surveillance manuals. • It could be helpful to collaborate with some other agencies who have already developed regulations and guidelines for the safe operation of TMF’s such as ICOLD, CDA, or MAC.
An Operators perspective • Operators require information on how to carry out the activities, frequencies of activities, selection of design criteria • Some areas to be developed to make these guidelines relevant to operators are • how to assess risk • What factors of safety to use in construction • Details on preparation of operations manuals • Parameters such as return periods for inflow design floods • Seismic event parameters • Recommendations on planning tools to be used – such as water management modelling tools
Deno Gold Mining Company, Kapan, Armenia • Kapan - Located in SW Armenia • Historical mining town • Approx 250 years of mining • 300km from Yerevan • Two main deposits with numerous smaller deposits in the mines vicinity
DGMC - a little history • 2004 KOMPE mine bankrupted • 2004- Operated as DGMC • Dec 2005 Starter loan by EBRD initiated upgrade existing equipment and environmental programmes • 2005- WAI work with site staff to write EAP’s and proposed monitoring programmes • 2006 Construction of Geghanush TMF • Sept 2006 Dundee bought 80% company, began corporate responsibility programme • April 2007 Begun environmental baseline study • Sept 2007 7 fulltime environmental staff and 25 local consultants, ~ 15 international consultants • End 2007 Commissioning of Geghanush
Artsvanik Dam • Small Tails Dam perched on very large Kadjeran TMF dam structure • Designed in 2003 by Armenian design institute • Capacity 1.1 Million m3 Maximum dam height 20m • Regular inspections from RA inspectors • Regular inspections from International Tailings Dam Engineer • Continuous monitoring by site staff • Dam movement (triangulation surveys) • Water quality and level • Peizometer water level checked daily • Rainfall data collected and weather station in use • Drilling crest of wall and analysis undertaken of materials Procedures in place to stop production in heavy rainfall or if water level rises Operate with lowest possible phreatic water level to maximise capacity during rainfall events.
Geghanush Dam • New dam over existing historic dam – capacity 11.0 million m3 • Construction included front and rear dam walls, completion of diversion tunnel for river, gravity decant structures • Plans and design were review by international tailings dam engineer and modified to include recommendations including finger drains • Recycling water to process plant should decrease discharge significantly • Same monitoring programme as Artsvanik to be implemented • Discharge water system is gravity decanted however backup submersible pumps will be available for extreme rainfall events