120 likes | 303 Views
Status of the Focus Coil Magnet Procurement. MICE Collaboration Meeting 25 th June 2012. Tom Bradshaw John Cobb Wing Lau Matt Hills. Elwyn Baynham Mike Courthold Victoria Bayliss Victoria Blackmore Jason Tarrant etc. Introduction.
E N D
Status of the Focus Coil Magnet Procurement MICE Collaboration Meeting 25th June 2012 Tom Bradshaw John Cobb Wing Lau Matt Hills Elwyn Baynham Mike Courthold Victoria Bayliss Victoria Blackmore Jason Tarrant etc...
Introduction Talk will cover: Recent progress at TESLA, Configuration and Schedule
Recent Progress and Status • Radiation shields fitted • Cold mass installed • Cold mass sensor wiring complete • Supports tensioned • Alignment of cold mass completed
Alignment of Cold Mass Picture shows the space for the installation of the force transducers for accurate tensioning of the straps. We will monitor these during cool-down – the straps will contract by ~1.26mm Jig for installing force transducer Dummy force transducer shown in position
Pre-stress of suspension Strap 1 0.51 Mid link 0.05 Strap 2 0.64 OVC link 0.06 Reduction in force due to OVC and foot deformation of 0.17mm Getting ~200kN from stress on cooldown which means that only a minimum room temperature pre-stress is required. This will be monitored during cool-down.
Alignment of Cold Mass Wing and Jason witnessed the alignment and strap tensioning on the 18th. Cold mass accurately centred Worryingly, the position of the flange hole centres is +/- 0.7mm on best fit pitch circle diameter which is out of tolerance. Best guess is that stress relieving of the OVC over time has caused this – we are investigating. Survey report is available. We are looking into either over- drilling on the existing bellow flange holes to match the surveyed hole positions on the OVC, or create a new set of holes at half pitch to the existing holes. In other words, the bellow flange will simply have holes to mate the two adjacent modules whatever their hole positions are. The Helium side is aligned to within 128 microns and -87 microns in the x and y coordinates respectively and the Hydrogen side is aligned to -113 and 67 microns. The required tolerance is ±250 microns.
Recent Progress and Status Wiring showing the tails exiting the cold mass
Odds and Ends Poorly performing Cryomech cooler has been returned from US – second one now has to be shipped back. Control and instrumentation is all now available and will be shipped to RAL soon. Power supplies have arrived and will also be shipped to RAL soon.
HTS Lead thermal link Some off-line measurements are being made on the thermal link between the HTS leads and the cryocooler mid stage. This is a critical joint. Found that Cu/Stycast/0.2mm FR4/Stycast/Cu joint is not as good as sandwich with 50µm Kapton Kapton is ~ x2 better than the FR4 and can withstand 4kV
R9 Facility Chiller for cryocoolers Area cleared and Yellow line for 5 Gauss limit.. Scaffolding CERN Field Measurement equipment