80 likes | 214 Views
Team GPXCleaner. Project Status Update #2. What has been done?. Many GUI improvements User controls and embedded map Point-reduction algorithm implemented Approx. 90% of implementation done. What is there to do?. Simple GUI vs. Expert GUI Improving usability Tooltips, m nemonics, ...
E N D
Team GPXCleaner Project Status Update #2
What has been done? • Many GUI improvements • User controls and embedded map • Point-reduction algorithm implemented • Approx. 90% of implementation done
What is there to do? • Simple GUI vs. Expert GUI • Improving usability • Tooltips, mnemonics, ... • Wildpoint detection and deletion • Parsing date/time in GPX format • Testing • Performing actual scenarios • Boundary cases of point-reduction algorithm