1 / 13

Project Status Update

SRWG Activity Report (as presented) March 21-23, 2012 TSS Meeting #160 WECC Offices Salt Lake City, Utah Mark Graham, SRWG Chair/David Franklin TSS Chair. Project Status Update.

ervin
Download Presentation

Project Status Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SRWG Activity Report(as presented)March 21-23, 2012TSS Meeting #160WECC OfficesSalt Lake City, UtahMark Graham, SRWG Chair/David Franklin TSS Chair

  2. Project Status Update • On December 30, 2011, WECC and Siemens PTI finalized the BCCS contract negotiations. The development of the BCCS will occur in stages throughout 2012, with the final product to be delivered in December 2012.  WECC will coordinate training in the first quarter 2013. 

  3. Project Status Update (con’t) • The BCCS will be a web-accessible, centralized database that automates existing processes. It will also provide a central location for maintaining base case information. This will increase the accuracy and timeliness of base case development. The BCCS will also provide a mechanism for supporting other WECC functions. The BCCS offers the following features and benefits:

  4. Project Status Update (con’t) • Features • PSLF/PSSE platform compatibility • Change tracking • Automated error checking • Secure Web interface • Interchange coordination • Database flexibility

  5. Project KEY Information should include: • Description label contents • Company, date • Interconnection Queue number • ISD, OSD, Phases • Project Status Milestones, • See next slide • Data Status Type • Location by State or Province • Dependencies (Project sequence) • Need input forms for populating this information Page 2 of 15

  6. Project Model data • Rating updates are placed in Profiles • Transactions, firm transfers and generation schedules will be balanced within BCCS • These power schedules are placed in Net schedule Interchange Profiles Page 4 of 15

  7. Develop Data Specifications • Consider Data Submission Schedules • annually or monthly • Profiles for designated seasons and years • Structure to store TPL Contingency lists • within BCCS • Control Access? • To improve program automation • Do we need this Page 7 of 15

  8. Features needed for robust model solutions • Solution capability within BCCS • There is concern that overall solutions will be more difficult • Voltage profiles • for seasonal starting points • By area If/when needed: • Develop extended models • generator groups, reactive groups, branch groups • Consider specialized features • distributed slack • coordinated voltage and VAr control Page 10 of 15

  9. Develop “BCCS implementation plan” • Determine Master Base Case time frame (tentatively 2012 HS) • Create Change file to 2012 case to create 2018 base • EPC, IDEV, EPCL, PYTHON, PRJ • Need out-service and in-service (verify) but is capable with the project file builder • PSSE currently does not have out of service dates. PSLF has this capability in-service and out-service dates that should be converted in the project files. • Place Joe Smith on July 2012 SRWG meeting. Page 11 of 15

  10. Develop “BCCS implementation plan” (con’t) • Project Naming, Structure • NERC compliance acronym_areano_projname(E.G., project name in annual progress report) • For example: Sce_24_dcr.prj • Submit a project description or translation file within the project files

  11. Develop “BCCS implementation plan” (con’t) • Validate Master Base Case data • Define user responsibilities and access settings • Define file-naming specifications as needed • Define Project Naming specifications • Schedule training after contract closure • Obtain vendor tools for building data • Start developing Project Files • Steady State and Dynamic data are separate • Develop Seasonal Profile data • Bus-Load-Generation (including losses) • Net schedule and Interchange data • Device control • Develop rating files • Begin using BCCS

  12. Data Submittal Process • Set schedule for base case compilation • Individual Contributors • Input Projects and Profiles • Validate accuracy • Area Coordinators review and approve data submittals Page 13 of 15

More Related