1. PROCON Services Inc /IAC - Fremont LLC Plant Reorganization Project 2008
2. Scope of Work Performed Press Relocations
Press Water, Air, & Power
Doghouses
Chiller Project
Chillers from Colorado
Chiller Tanks
Cooling Tower Installation
Victaulic Piping Installation
New Truck Docks
Design
Concrete
Material Handling Equipment
Compactor Installation
Maintenance Support
3. Press Relocations PROCON relocated automotive parts manufacturing equipment throughout a customer’s plant in Fremont Ohio. All machine power, water & air were also relocated.
A total of 17 machines were moved. Several machines swapped position and had to be shifted, spun and reconnected at the same time.
Some of the larger equipment was moved out the door, down the street and back into the other end of the facility.
Several machines were moved out of the plant and to other locations throughout North America
Production continued at this facility while PROCON worked to bring the relocated equipment back online.
4. Press #301
5. Presses to Mexico With new equipment coming into the Fremont facility, several presses left the plant and were shipped to Mexico. PROCON dismantled the 5 presses, loaded them on trucks, shipped them to locations in Hermosillo & Ramos Mexico and supervised the re-installation of the equipment across the border.
6. Water, Air & Power All the utilities to each machine were labeled, disconnected and reconnected at the new locations. This shortened downtime & ensured easier start-up.
7. Rooftop Ventilation Eight large “doghouses” were put on the roof to provide ventilation for the plant. The doghouses were framed in on the ground and raised to the roof with a crane.
Once on the roof, fans were installed in the framed openings. Siding was installed and the roof professionally sealed.
8. Chiller Project An opportunity arose to purchase (2) used chillers from a vacant shopping mall in Denver, Colorado.
The mall was scheduled for demolition.
9. Chiller Tank Fabrication
10. Cooling Towers
11. Victaulic Piping Installation PROCON then installed all of the piping to & from the equipment. 18” Victaulic piping was used at the chillers. All of the new piping to the production area was also installed by PROCON.
12. New Truck Dock Design
13. Truck Dock Concrete
14. Material Handling Equipment
15. Complete Truck Dock
16. Compactor Installation
17. Maintenance Support PROCON also performed support services for the maintenance department:
Unloading, setting & leveling transformers
Rigging & removing obsolete equipment
Fabricating
Machinery stands
Maintenance platforms
Drip pans
Power study
Purging gas lines
Start-up support
Building repairs
Repairs to production equipment