10 likes | 109 Views
SUN DEVIL PROJECT COST COMPARISON. LINE ITEMS NOT IN LEVEL A. 10-03-01. Major line items not accounted for in the Level A cost estimate. These items would only be discovered in a detailed design review. $ 33.2. Navajo right of way costs and Navajo premium payment. Land. Labor. $ 13.2.
E N D
SUN DEVIL PROJECT COST COMPARISON LINE ITEMS NOT IN LEVEL A 10-03-01 Major line items not accounted for in the Level A cost estimate. These items would only be discovered in a detailed design review. $ 33.2 Navajo right of way costs and Navajo premium payment. Land Labor $ 13.2 $ 46.4 Rocky terrain adding extra costs during construction. $ 16.1 $ 14.5 Gross receipts in Arizona and New Mexico not included. $ 44.7 Escalation not considered in Level A estimate. $ 7.6 River crossing costs not included in Level A. Mountain terrain & BLM double ditching $ 4.5 10% contingency on above items $ 13.7 Total $150.5 Level A + Total = $899.3 ($748.8+$150.0) Sun Devil04.ppt