Michigan Interconnection Rules Rules vs. Procedures

Understand Michigan Interconnection Rules and Procedures, including hierarchy, timelines, waivers, documents, and fees. Learn about fast track processes, requirements, and stakeholder involvement.

jbrian
Download Presentation

Michigan Interconnection Rules Rules vs. Procedures

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Michigan Interconnection Rules Rules vs. Procedures Julie Baldwin June 20, 2019

  2. Hierarchy of Interconnection Documents Laws Rules Procedures Utility Specific Documents (Business Practice Documents)

  3. Rules • Rules may also be referred to as “standards.” • Generally, requirements that are applicable to all utilities must go through the rulemaking process. • Incorporating a stakeholder process to develop a draft ruleset and formal rulemaking can take 24 months. • Rules may include a waiver – however, any waiver must not violate the law. • Current MPSC Electric Interconnection and Net Metering Standards • Definitions Laws Rules Procedures Utility Documents

  4. Procedures • The Generator Interconnection Procedures, Applications and Interconnection Agreements for Category 1 and 2 Projects (up to 150 kW) were approved by Commission Order. • Commission approval process could take 6 – 12 months. Laws Rules Procedures Utility Documents

  5. Consider Addressing in Rules • Requirement that Interconnection Procedures be filed within 90 days for MPSC approval • List of application Standards • Pre-Application Report • Fast Track Process Steps & Timelines • Study Process Steps & Timelines • Alternative Dispute Resolution Process • Waiver Process

  6. Consider Addressing in Procedures • Fast Track Application • List of documents required for completeness • Study Process Application • List of documents required for completeness • System Impact Study Agreement • Facilities Study Agreement • Construction Agreement • Interconnection Operating Agreement • Fast Track and Study Process Application Fees • System Impact Study Fees (phase I and II) • Facilities Study Fees

  7. Technical Matters for Procedures • Energy Storage • Voltage and Frequency Ride Through Settings (if not handled in utility documents) • More items TBD

  8. Matters for Utility Documents • Voltage and Frequency Ride-through Settings (if not handled in procedures) • Voltage and Reactive Power Control

  9. Thank you! Questions?