Performance Monitoring Report - Testing Internet and EBnet networks between NASDA and various sites - Network Subgroup - May, 2002 Shin-ichi Sobue NASDA/SPPD Kengo Aizawa RESTEC CEOS Subgroup Meetings May 7-10, 2002. Frascati.
Performance Monitoring (1) - Testing Internet Networks- - Purpose: to confirm network performance and plan new networks among the earth observation community. - Changes: NASDA upgraded the ATM Line Between Tsukuba and the EOC on Oct 27th, 2001. 2M → 4M(bps) - Tools: tcpwatch, ping, traceroute CEOS Subgroup Meetings May 7-10, 2002. Frascati.
Test Route A (From EOC to various sites • via the Internet) • a. Source Node: • HEOC/NASDA : azusa.eoc.nasda.go.jp • b. Destination Nodes: • 1. GSFC/NASA : g0acg01u.eoc.nasa.gov • 2. JPL/NASA : yngvi.jpl.nasa.gov • 3. CCRS : ceodev.ccrs.nrcan.go.ca • 4. CSIRO : terra.eoc.csiro.au • 5. AIT : noaa.acrors.ait.th CEOS Subgroup Meetings May 7-10, 2002. Frascati.
- Internet Routing - Figure 1 CCRS CSIRO Commercial Providers GSFC Abilene APAN/ TransPac NASDA IMnet NECTEC TKSC WIDE AIT Upgrade 2M -> 4M HEOC SGI JPL JPL CEOS Subgroup Meetings May 7-10, 2002. Frascati.
Test Route B • (From Tsukuba to GSFC via the Internet) • a. Source Node: • TKSC (NASDA) : tkes12.tksc.nasda.go.jp • b. Destination Node: • 1. GSFC : 198.10.49.61 CEOS Subgroup Meetings May 7-10, 2002. Frascati.
Summary(1):Test Route A azusa@HEOC • Madian Daily Throughput - • (Median of Daily Maximums and Minimums) Destination Throughput ( Kbps) Period (mm/dd/yy) max. - min. 1. GSFC 1195 - 227 7/29/01 - 10/27/01 1191 - 212 10/28/01 - 1/05/02 2. JPL 1089 - 340 7/29/01 - 10/27/01 1211 - 293 10/28/01 - 1/05/02 3. CCRS 1273 - 697 7/29/01 - 10/27/01 1294 - 664 10/28/01 - 1/05/02 4. CSIRO 608 - 171 7/29/01 - 10/27/01 595 - 181 10/28/01 - 1/05/02 5. AIT 874 - 186 7/29/01 - 10/27/01 1026 - 131 10/28/01 - 1/05/02 There are wide margin between max. value and min. value due to heavy traffics a few times in a day. (as a result of MRTG between Tsukuba and EOC.) CEOS Subgroup Meetings May 7-10, 2002. Frascati.
- Median Hourly Throughput - (Maximum and Minimum of median of Hourly Values for Entire Period. See Figure2) Destination Throughput ( Kbps) Period (mm/dd/yy) (Max - Min) 1. GSFC 665 - 459 7/29/01 - 10/27/01 870 - 719 10/28/01 - 1/05/02 2. JPL 901 - 709 7/29/01 - 10/27/01 928 - 790 10/28/01 - 1/05/02 3. CCRS 1108 - 955 7/29/01 - 10/27/01 1085 - 990 10/28/01 - 1/05/02 4. CSIRO 388 - 312 7/29/01 - 10/27/01 367 - 271 10/28/01 - 1/05/02 5. AIT 691 - 411 7/29/01 - 10/27/01 824 - 456 10/28/01 - 1/05/02 CEOS Subgroup Meetings May 7-10, 2002. Frascati.
Figure 2 This figure shows median of HourlyValues for Entire Period. CEOS Subgroup Meetings May 7-10, 2002. Frascati.
Summary(2):Test Route Beagle@TKSC - Median Daily Throughput - Destination Throughput ( Kbps) Period (mm/dd/yy) max. - min. 1. GSFC 2693 - 1206 8/25/01 - 10/27/01 2184 - 1415 10/28/01 - 1/05/02 - Median Hourly Throughput - Destination Throughput ( Kbps) Period (mm/dd/yy) max. - min. 1. GSFC 2586 - 2083 8/25/01 - 10/27/01 2117 - 2025 10/28/01 - 1/05/02 CEOS Subgroup Meetings May 7-10, 2002. Frascati.
Concerns Test Routes A (from EOC to each agencies) - After upgrading the ATM Line between Tsukuba and the EOC the average throughput improved and the maximums and minimums were more stable. [TKSC - GSFC(g0aeg01u), Figure 3] Test Routes B (from Tsukuba to GSFC) - After Oct 28th on the TKSC – GSFC(198.10.49.61) route, both average throughput and hourly throughput fell by almost 20%. (Figure 4) (Traceroutes before and after Oct 28th are shown in Figures 5.) CEOS Subgroup Meetings May 7-10, 2002. Frascati.
Figure 3 Average throughput improved CEOS Subgroup Meetings May 7-10, 2002. Frascati.
Figure 4 Drop (20% down) CEOS Subgroup Meetings May 7-10, 2002. Frascati.
Figure 5Traceroute results Before Oct. 28th, 2001 After Oct. 28th, 2001 + About 40ms CEOS Subgroup Meetings May 7-10, 2002. Frascati.
Performance Monitoring (2) - Testing EBnet Networks - -Purpose: to confirm network performance and plan new networks among the earth observation community. -Tools: tcpwatch, ping, traceroute CEOS Subgroup Meetings May 7-10, 2002. Frascati.
- Test Route C (From EOC to various sites via EBnet) a. Source Node: HEOC (NASDA) :hdds4c11.eoc.nasda.go.jp b. Destination Nodes: 1. GSFC(g0eag01 ) : g0acg01.gsfcb.ecs.nasa.gov 2. GSFC(gscsafs) : gsfcsafs.nascom.nasa.gov 3. ASF : 192.107.193.23 CEOS Subgroup Meetings May 7-10, 2002. Frascati.
EOC Figure 6 EBnet Routing 5M GSFC 3M JPL 3M ASF CEOS Subgroup Meetings May 7-10, 2002. Frascati.
Summary(3):Test Route Chdds4cef@HEOC(EBnet) - Median Daily Throughput - Destination Throughput ( Kbps) Period (mm/dd/yy) max. - min. 1. GSFC (goeag01) 1729 - 1333 8/26/01 - 3/02/02 2. GSFC(gscsafs) 1653 - 937 8/07/01 - 3/02/02 3. ASF 1604 - 991 9/23/01 - 3/02/02 - Median Hourly Throughput - Destination Throughput ( Kbps) Period (mm/dd/yy) max. - min. 1. GSFC(goeag01) 1695 - 1569 8/26/01 - 3/02/02 2. GSFC(gscsafs) 1591 - 1441 8/07/01 - 3/02/02 3. ASF 1606 - 1360 9/23/01 - 3/02/02 CEOS Subgroup Meetings May 7-10, 2002. Frascati.
Concerns (continued) • Test Route C • As it is shown in Figure 7, Max average throughput continues to • be around 1700 Kbps. • The transmission buffer size was increased, but the • throughput didn’t improve. CEOS Subgroup Meetings May 7-10, 2002. Frascati.
Figure 7 CEOS Subgroup Meetings May 7-10, 2002. Frascati.
Proposed Investigations - Internet The performance decrease on the APAN - Abilene route should be investigated. - EBnet We performed an FTP performance test over EBnet between EOC and JPL(137.78.31.81) . The Average performancewas around 2.0 Mbps and Max performance was 2.35 Mbps. The results of the FTP test and traceroutes in Figures 8 to 11 indicate there is not a problem between 202.251.177.12 and 202.251.177.186. The traceroute times between 202.251.177.186 and g0aeg01, gsfcsafs, ASF are rather long. Should they be investigated? CEOS Subgroup Meetings May 7-10, 2002. Frascati.
Figure 8 CEOS Subgroup Meetings May 7-10, 2002. Frascati.
Figure 9 CEOS Subgroup Meetings May 7-10, 2002. Frascati.
Figure 10 CEOS Subgroup Meetings May 7-10, 2002. Frascati.
Figure 11 CEOS Subgroup Meetings May 7-10, 2002. Frascati.