160 likes | 172 Views
This document discusses the enhanced luminosity goals and projections for the RHIC Collider in the next 5 years, before the implementation of e-cooling. It covers assumptions, limitations, and improvements for the injectors, luminosity and background, time in store, and overall run projections. The document also provides a summary of the major improvements for RHIC.
E N D
Near-term machine performance— The next 5 years, before e-cooling — Wolfram Fischer Run Coordinator for RHIC Run-4 Open Meeting on RHIC PlanningBerkner Hall3 December 2003
Enhanced luminosity • Enhanced Luminosity Goals (before e-cooling) • For Au-Au, average per store (4 design)L = 81026cm-2s-1 at 100GeV/u • For p-p average per store, 2 IRs (16 design)L = 61031cm-2s-1 at 100GeVL = 1.51032cm-2s-1 at 250GeVwith 70% polarization
Contents • Assumptions for projections • Limitations and improvements • Injectors • Luminosity and background • Time at store • Run-4 • 5-year projections • Summary
RHIC Collider Projections [annual updates based on experience gained in the previous run]
Assumptions for projections • 2 weeks for cool-down, 1 week for warm-up • For each mode (Au-Au, p-p, d-Au, etc.) • 2 weeks of set-up[only machine operation] • 3 weeks of ramp-up[machine operation with experimental set-up during owl shift] • Continuous luminosity development in production[over 14 weeks during the day] • Minimum and maximum projections • Minimum repeats demonstrated performance • Maximum requires completion of improvement projects • Maxima ambitious, likely outcome between min and max • For 5-year luminosity projections • 5+14 weeks of operation in each mode • Only 2 collisions in p-p operation Large penalty for frequent mode switches
Collider performance comparisons 14 wks 14 wks • Common features • long runs (>14 wks/yr) • non-linear increase after shut-downs- many years for substantial increases • RHIC is of comparable complexity! 14 wks M. Lamont
Limitations (1) – injectors • Bunch intensity and polarization • Achieved: Au 0.7109/bunch 10mm 0.3eV·s • Booster low level rf upgrade • Additional bunch merge 1.3 109/bunch • Achieved: p 0.81011/bunch 10mm 0.3eV·s 40% pol. • Achieved: p 2.01011/bunch 20mm 0.5eV·s 20% pol. ? • AGS warm helical snake in Run-4 40% pol. in RHIC • AGS cold helical snake in Run-5 70% pol. in RHIC • Later • New solenoid for polarized source • 2nd AGS cold helical snake? • EBIS (Electron Beam Ion Source) • Earliest 2008, see presentation by J. Alessi
Limitations (2) – luminosity and background • Vacuum problems with high intensities Test of NEG coated beam pipes (low SEY, pumping) Solenoids • Losses during ramp Better orbit, tune, coupling, chromaticity control PLL tune meter, tune feedback • Experimental background Secondary collimators (½ this year, ½ next) Shielding (PHENIX, BRAHMS this year) • Instabilities Improved chromaticity control, coherence monitor Transverse damper • Intra-beam scattering (Au-Au) Stochastic cooling development e-cooling for RHIC II
Limitations (3) – time in store • Reduction of quench occurrences Reduce abort kicker pre-fires Avoid excessive beam losses • Improve operational efficiency Faster down ramps (gain about 2 days/run) More automation at beginning of store (steering, collimation, gap cleaning) Better software tools for ramp tuning Faster injection set-up • Reduce system downtime Eliminate ice ball maintenance at current leads Improve corrector power supply reliability Improve AtR reliability • …
Run-4 goals • President’s budget allows for 27 weeks of cryogenic operation (need 3 weeks for cool-down and warm-up) • Run-4 modes: • 5+14 weeks Au-Au at 100GeV/u beam energy,target luminosity of 300(mb)-1 delivered • 5 weeks p development(partial warm AGS snake, gas jet, working point)
Run-4 goals experimental target [after 5 weeks of start-up and ramp-up]
Current status RHIC Run-4 • 5-week start-up/ramp-up period started on Monday 12/1/03 • Reached 0.8·109/bunch in Blue on Monday • Blue: Injected 111 bunches with 0.5·109/bunch (pressure rise in bi8 and bo2, up to 10-6 Torr) • Yellow: Injected 111 bunches with 0.1·109/bunch (no pressure rise observed) • First ramps this morning • 6 bunches each • 50% Blue transmission • 40% Yellow transmission Today at noon
Projected 5-year Au-Au luminosity evolution • Assume • 14 weeks production in every year • linear luminosity increase during run • 4 experiments • completion of improvements achieved projected maximum
Projected 5-year p-p luminosity evolution • Assume • 14 weeks production in every year • linear luminosity increase during run • only 2 experiments • completion of improvements achieved projected maximum
Major RHIC improvements Injectors Luminosity and background Time in store New things to be filled in as we understand the machine better
Summary • Enhanced Luminosity Goals (before e-cooling) • For Au-Au, average per store (4 design)L = 81026cm-2s-1 at 100GeV/u • For p-p average per store, 2 IRs (16 design)L = 61031cm-2s-1 at 100GeVL = 1.51032cm-2s-1 at 250GeVwith 70% polarization • Required • Sufficient running time in each mode [many weeks/year] • Resources to carry out improvement projects