1 / 23

New Richmond Load Serving Study

Explore the load serving issues, methodology, and recommendations for Western Wisconsin. Includes area description, problems, methodology, and detailed project schedules.

jcooper
Download Presentation

New Richmond Load Serving Study

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. New Richmond Load Serving Study Northern MAPP Subregional Planning Group August 16, 2006 Daniel Kline

  2. Outline • Description of Area • Various Load Serving Problems • Study Methodology & Initial Alternatives • Final Alternatives Considered • Final Recommendation & Initial Project Schedule • Questions

  3. Description of Area • Located in Western Wisconsin • St. Croix County • Just across Minnesota border, near I-94 • Area fed by 161 kV sources and 69 kV subtransmission • Load belonging to Xcel and DPC • Lines belonging toXcel and DPC

  4. Description of Area • Area Xcel Loads (2011): • New Richmond (9.1 MW) • Somerset (7.7 MW) • Kinnickinnic (4.4 MW) • Osceola (15.4 MW) • River Falls (30 MW) • Area DPC Loads (2011): • New Richmond (15 MW) • Houlton (5.4 MW) • Farmington (8.1 MW) • Roberts (4.6 MW) • Hammond (3.2 MW)

  5. Description of Area

  6. Description of Problems • Low voltage at New Richmond during outage of Pine Lake – New Richmond 69 kV line • Low voltage at Osceola during outage of Osceola – Osceola Tap 69 kV line • Overload of River Falls 115/69 kV transformer during outage of Osceola – Osceola Tap 69 kV line • Overload of Pine Lake 161/115 kV transformer during outage of King – Willow River 115 kV line • Normal Overload of Pine Lake – Rush River 69 kV line

  7. Description of Problems • High load growth throughout area • Installation of Chisago Line Project will require extended outage of Osceola – Osceola Tap 69 kV line • No room for expansion at New Richmond Substation • No room for expansion at Rush River Substation

  8. Study Methodology • 2006 MAPP Series Cases • 2011 Near-Term • 2016 Out-Year • Study Group Asked to Review: • Jerry Iverson, DPC • Bob Roddy, DPC • Dave Krause, KPE • Jeff Haas, Xcel • Walt Grivna, Xcel

  9. Study Methodology • Assumptions and Adjustments made • Assumed Chisago Line Project not in service in 2011 (In-service in 2016) • New City of New Richmond Substation in service • Xcel’s Somerset Substation in service • Added DPC N-60 line upgrade (477 ACSR)

  10. Study Methodology • Base Case Results

  11. Study Methodology • Base Case Results

  12. Initial Ideas • Multi-Faceted Approach • 5.4 MVAR Capacitor at Osceola • 10.0 MVAR Capacitor at New Richmond • New 69 kV switching station south of New Richmond that would tap DPC N-60 line • 115/69 kV Transformer near Kinnickinnic Substation • 161/69 kV Transformer at Clear Lake Substation • 69 kV line from Somerset to new substation north of New Richmond • 69 kV line from Cylon to new substation north of New Richmond

  13. Initial Ideas • Options investigated with and without Chisago project • Necessity of Poplar Lake Substation and 161/69 kV transformer investigated

  14. Final Alternatives • Three options tagged for detailed review • Alternative 1, Step 2A – Three Lakes 115/69 kV Substation, Stanton 69 kV Substation, & Somerset to Stanton 69 kV Line • Alternative 1, Step 2B – Three Lakes 115/69 kV Substation, Stanton 69 kV Substation, & Cylon to Stanton 69 kV Line • Alternative 2, Step 1 – 115/69 kV Substation south of New Richmond

  15. Final Alternatives - 1

  16. Final Alternatives - 1

  17. Final Alternatives - 2

  18. Final Alternatives - 2

  19. Final Alternatives - 3

  20. Final Alternatives - 3 • Voltage Violations too numerous to mention

  21. Final Recommendation • Alternative 1 Recommended • 10 MVAR Cap Bank at New Richmond – ASAP • Three Lakes Substation – ASAP • 5.4 MVAR Cap Bank at Osceola – May 31, 2009 • Rebuild Osceola to Sand Lake 69 kV Line – May 31, 2009 • Relocate Rush River Substation and cut over to 161 kV – May 31, 2010 • Construct Somerset Sub – May 31, 2010 • Construct Stanton Sub – December 31, 2010 • Construct Somerset to Stanton 69 kV Line – May 31, 2011 • Complete installation of Chisago Line Project – May 31, 2011 • Construct Poplar Lake Sub & 161/69 kV Transformer – May 31, 2011

  22. Next Steps • Currently compiling necessary information for business case • Will have more meetings with Study Group prior to any filings

More Related