1 / 30

LS1 The upgrade of 600 A ENERGY EXTRACTION SYSTEMS

LS1 The upgrade of 600 A ENERGY EXTRACTION SYSTEMS. Overview. 600 A EE; what, where, how ? Reliability Hardware Failures to be cured Why upgrade? Failure causes Solutions LS1 actions Resources Planning Showstoppers Non LHC activities during LS1. Energy Extraction 600 A circuit.

jela
Download Presentation

LS1 The upgrade of 600 A ENERGY EXTRACTION SYSTEMS

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LS1The upgrade of 600 AENERGY EXTRACTION SYSTEMS

  2. Overview • 600 A EE; what, where, how ? • Reliability • Hardware Failures to be cured • Why upgrade? • Failure causes • Solutions • LS1 actions • Resources • Planning • Showstoppers • Non LHC activities during LS1

  3. Energy Extraction 600 A circuit

  4. 600A Energy Extraction Systems • 202 systems installed in the LHC tunnel in corrector circuits with stored energy between 2.2 and 150 kJ • In 15 different locations; • 8 x UA parallel service tunnel and 6 x RR and 1 x UJ tunnel caverns • Systems developed in close collaboration between CERN and the Budker Institute of Nuclear Physics (BINP), Novosibirsk, Russia.

  5. Reliability • Systems reliability from protection point of view: No opening failures during Fast Power Abort events or tests (> 100.000 openings since 2005) • 2 independent opening mechanisms/circuits per breaker; guaranteeing 6-fold redundancy • Calculated by Antonio Vergara in December 2003: • System Failure probability in 20 years of operation < 0.01% (Preventive maintenance!!)

  6. Reliability (2) • Systems reliability from hardware failure point of view: • 6 hardware failures in 2010 • 1 hardware failure in 2011 • 3+1* hardware failures in 2012 • Changes with respect to 2010 operational year : • Preventive maintenance • with help of automatic analysis and tracking software tool. • For operation: 2 failures per year – not in shadow • Mean Time To Recovery : 4 hours • (including preparation, access and travel) • All failures were “fail-safe” for the s.c. circuits • reducing the availability of the system.

  7. Hardware Failures treated during LS1 • 5-10/year - 95% of all failures: Breaker refuses to close • Loosening of holding coil mechanism – LHC re-start delayed • 1/year - Breaker is physically open but indicates “CLOSED” • micro-switch not actuated / main axle – LHC re-start delayed • 1/year - Breaker main contact re-bounces on micro-switch • main axle – LHC re-start delayed

  8. Why do we upgrade? • Correcting measures are relatively easy • < 100 kCHF • This upgrade will improve the availability of 600 A EE systems for LHC operation by 4-8 hours per year…. • Less preventive maintenance

  9. Failure causes • 1- Loosening of holding coil mechanism • Weak design of U-shape • 2- Micro-switch not actuated • Tolerances in dimensions of housing • 3- Main axle fixation • Weakness during production– not an increasing fault

  10. Solutions • 1- Loosening of holding coil mechanism • Weak design of U-shape and dimensional tolerances • Needs to achieve • Plate Glue Action in all 606 breakers • Open all breakers (anyway foreseen for regular maintenance) • Plate gluing – Once open: 2-3 minutes per breaker

  11. Solutionscntd. • 2- Micro-switch not actuated (temporarily) • Tolerances in dimensions of housing • Already tracked by automatic analysis software tool • Leading to an unscheduled but still preventive maintenance intervention (in the shadow) • On-going but to be extended with advice in form of logbook entries (MPE-MS)

  12. Solutionscntd. • 3- Main axle fixation • A loose main axle means no current in 2 oo 3 phases in the CB leading (> 200A circuit current) to overheating of the 3rd phase. • Weakness during production – no increasing numbers • Manufacturer has improved this process for new breakers • For existing breakers no solution.. But.. • We can track it because of known early symptoms • Already tracked by the same automatic analysis software tool but with very few cycles left – we can measure the System Resistance! • Leading to an unscheduled corrective or preventive maintenance intervention

  13. Solutionscntd. • 3- Main axle fixation tracking improvement - Measurement • Needs to achieve • Improvement of existing Voltage Measurement Channel • Replacement of Voltage Divider by low impedance divider and noise reduction components (270 pcs MPE-EM) • Replacement of Measurement Board by low noise separation amplifier (270 pcs: MPE-EM) • Replacement of DQAMS by 12 bit to 24 bit ADC (MPE-EP & EM: 220 pcs) • Voltage measurement taps to be improved • Hi-level SW for on-line analysis (MPE-MS)

  14. Solutionscntd. • 3- Main axle fixation (and loose bolts) • Save the EE system • in case we don’t track (or too late) it with software tools • Overcurrent in one or two phases of the breakers will lead to over-temperature on the Equalizing Resistor and eventually destroy all breakers in one system • Installation of a Thermostat on each Equalizing Resistor will trip the system early before hardware damage is done • A spare internal interlock channel is available and wired up to the power board. • Needs to achieve • Installation of Thermostats • Reprogramming of Firmware in all 404 interface cards (MPE-EP) • Allow trip on over temperature of Equalizing Resistor • Profit to limit cycles of the breakers

  15. LS1 Actions

  16. Resources

  17. Planning (not incl. SCT and HWC) • ANYTIME – “ANYWHERE” • April 2013 – April 2014 – 6 man-months – • Team of 3 persons could come 2 x 1 month But .. • Man-power Calculations based on one team of Specialistsfrom BINP • Perfect preparation before start of activity • One Engineer or TE as team leader plus two Technicians • Working in a “train” Start – to – Finish one point, including IST

  18. Planning SCT & HWC • SCT & HWC – 2014 • SCT was presented as not needed for 600 A EE but … latest tests show.. Yes, if we could we should  • 1 day per UA or RR – 2 TE or E • 15 working-days - NO recourses allocated yet • HWC like SOF test PLI3.b1 – remotely from CCC – • Automatic Analysis of PM • PNO.b1 – 1 day per UA or RR – 2 TE or E • 15 working-days - NO recourses allocated yet

  19. “Showstoppers” • Preparation for LS1 • Planning – Tests – Tooling – Purchasing (thermostat-study still to be finished) • A LONG WAY TO GO!!! • No reference contract with Russia • If done by non-experts • More CERN staff needed for training, the actual job, follow up, debugging of collateral damage etc. Might delay re-start after LS1. • Spare Circuit Breakers: • DZNVA – Visit in March 2012 - Manufacturer’s premises in very bad state and only 20% occupied - might stop delivering (special) breakers • Currently: 28 spares (13 operational – 15 to be qualified before TS4) • Consumption average: 8-10 per year (including preventive changes)

  20. Non LHC activities during LS1 • Currently low in spare systems (<1%) and spare breakers (3-4%) • In order: 20 spare systems – ATA Autumn 2013 – to be mounted and tested in ISR test building • Urgent: to order 120-150 spare breakers in order to exclude the regular need of Russian Specialists and cover mid-term needs. Long term strategy for 600 A EE systems: • Switch partially (UA areas) to solid state breakers • R&D necessary: • 2012 development of Lab version (Bi-polar) • 2013/2014 development of prototype – 0.5 day/week • 2015 Market Survey/Tender What about the study to prevent Quench-Back on RQTF/D the installation of lower dump resistances in 600A circuits

  21. Thank you for your attention.. So far..!

  22. Questions before continuing with Cable Activities?

  23. Planning activities GJC • Preparation 600 A EE activities to start LS1: • 70% • Installation/Maintenance – 2013 • Coordination – during the activity 50% • IST – 2013 • Coordination – during the activity 50% • SCT – 2014 • Coordination/installation/Analysis: 70% during activity • HWC – 2014 • PLI3.b1 – remotely from CCC – Automatic Analysis of PM • Activities if automatic analysis fails • PNO.b1 – 1 day per UA or RR – 2 TE or E • Coordination/installation/Analysis: 70% during activity

  24. Solutions • 1- Loosening of holding coil mechanism • Weak design of U-shape and dimensional tolerances • Vibrations causing the closing failures – if starting increasing with cycles • To prevent vibrations the manufacturer proposed decreasing of gaps on the side of the U-Shape by gluing small plates between the U-shape and the housing • Several cycling tests have proven the efficiency of this method. Number of closing failures reduces from typically 4% to less than 0.5 % during lifetime of breaker • Needs to achieve • Plate Glue Action in all 606 breakers • Open all breakers (anyway foreseen for regular maintenance) • Plate gluing – Once open: 3-4 minutes per breaker • Glue = Silicon paste (Dow Corning Mil. Standard) approved by breaker manufacturer

  25. Solutions

  26. Solutionscntd. • 3- Main axle fixation tracking improvement • Weakness during production • If this occurs there’s an increase from 0.5 mΩ to max 1.25 m Ω of system impedance due to decrease of contact pressure in the breaker. • By improving the existing voltage (drop) measurement, correlating it to the circuit current, can lead to an early warning, preventing the circuit to trip • An intervention can be planned in the shadow • Needs to achieve • Improvement of existing Voltage Measurement Channel • Replacement of Voltage Divider by low impedance divider and noise reduction components (MPE-EM) • Replacement of Measurement Board by low noise separation amplifier (MPE-EM) • Replacement of DQAMS by 12 bit to 24 bit ADC (MPE-EP & EM) • Voltage measurement taps to be improved • Hi-level SW for on-line analysis (MPE-MS)

  27. Solutionscntd. • 3- Main axle fixation (and loose bolts) • Overcurrent in one or two phases of the breakers will lead to over-temperature on the Equalizing Resistor and destructing all 3 breakers in one system • Installation of a Thermostat on each Equalizing Resistor will trip the system early before hardware damage is done • A spare internal interlock channel is available and wired up to the power board. • Needs to achieve • Installation of Thermostats and Wiring up to the spare channel • Dismounting, drilling, threading of all 606 Equalizing Resistors • Mounting of pre-cabled Thermostats and a connector PCB • Wire installation from connector PCB to Burndy connector SK24 • Reprogramming of Firmware in all 404 interface cards (MPE-EP)

More Related