Surface Treatment. Multi Agencies Collaboration. Participating Agencies. Oregon Department of Transportation Ona Beach Maintenance Section Rose Lodge Maintenance Section Benton County Department of Transportation Private Contractors. 2010 Surface Treatment Projects. Highway 34
E N D
Surface Treatment Multi Agencies Collaboration
Participating Agencies Oregon Department of Transportation Ona Beach Maintenance Section Rose Lodge Maintenance Section Benton County Department of Transportation Private Contractors
2010 Surface Treatment Projects Highway 34 From Milepost 7.0- Milepost 14.0 Highway 226 From Milepost 13.5-Milepost 16.0
Oregon Department of Transportation Responsibilities • Materials Contracts • Iron Mountain Chip Seal Rock 3/8-1/4, • Liquid Asphalt-HFRS-1P • Testing of Materials
Oregon Department of Transportation Responsibilities • Stockpile Site Preparation • Stockpile Chip Seal Rock • Monitor Stockpile Moisture Content • Stockpile Location Cleanup
Oregon Department of Transportation Responsibilities • Front End Loader and Operator • Three Roller Operators • One Pneumatic Roller (Rental/within ODOT) • Six Ten Yard Trucks and Drivers • 2000 gal. Water Truck • Open Air Broom and Operator • Broom Shadow Vehicle and Operator
Oregon Department of Transportation Responsibilities • VMS Boards placed for advanced warning • Stick and Stomps and Setter Prior to start of Project • Work Zone Signage and Set up • Pilot Cars and Operators • Stick and Stomp Tab Cover Removal
Benton County Department of Transportation Responsibilities • Materials Contract (Freight/Distributors) • Daily Ordering of Materials • Material Samples for Testing
Benton County Department of Transportation Responsibilities • 2000 Gallon Liquid Asphalt Distributor and Operator ( as needed for chip seal and fog seal) • Chip Spreader with Operator and Dump Boss/Belt Operator • Pneumatic Roller and Steel Wheel Single Drum • Ten Yard Dump Trucks( as needed) • Open Air Broom ( as needed) • Specialty Signs ( Loose Rock, Fresh Oil)
Contractor Responsibilities • 4400 Gallon Liquid Asphalt Distributor (Chip Seal and Fog Seal, Albania) • Traffic Control Flaggers ( St Vincent's )
Surface Treatment Multi Agency Collaboration • Benton County Chip Spreader • ODOT Ten Yard Truck
Surface Treatment Multi Agency Collaboration Contractor 4400 Gallon Liquid Asphalt Distributor
Surface Treatment Multi Agency Collaboration • Benton County Rollers • ODOT Roller • ODOT Operators
Surface Treatment Multi Agency Collaboration • ODOT Pilot Vehicle
Surface Treatment Multi Agency Collaboration • ODOT Pilot Vehicle controlling traffic speeds through the work zone.
Estimated Costs for Hwy 34 • Cost per mile $37,200 • Cost per sq yd $2.65