2nd Quarter 2013 VRL Report

2nd Quarter 2013 VRL Report. Gentry Tubbs gtubbs@spp.org. TEMP04_18988. Monitored Element- EMAN to MCDO 115kV Contingent Element - JEFF to MORR 345kV Reason for Violating: Outage in the area caused high loading. OSGCANBUSDEA. Monitored Element- Osage - Canyon 115 kV

jennis
Download Presentation

2nd Quarter 2013 VRL Report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 2nd Quarter 2013VRL Report Gentry Tubbsgtubbs@spp.org

  2. TEMP04_18988 • Monitored Element- EMAN to MCDO 115kV • Contingent Element - JEFF to MORR 345kV • Reason for Violating: Outage in the area caused high loading.

  3. OSGCANBUSDEA • Monitored Element- Osage - Canyon 115 kV • Contingent Element – Bushland – Deaf Smith 230KV • Reason for Violating: Increase of wind in the south as we were coming up on evening peak load.

  4. OSGCANBUSDEA • Monitored Element- Osage - Canyon 115 kV • Contingent Element – Bushland – Deaf Smith 230KV • Reason for Violating: Outage in the area along with high wind in the south caused violations.

  5. OSGCANBUSDEA • Monitored Element- Osage - Canyon 115 kV • Contingent Element – Bushland – Deaf Smith 230KV • Reason for Violating: Outage in the area along with high wind in the south.

  6. OSGCANBUSDEA • Monitored Element- Osage - Canyon 115 kV • Contingent Element – Bushland – Deaf Smith 230KV • Reason for Violating: Outage in the area along with high wind in the south as we approached morning peak.

  7. LAKALASTJHAW • Monitored Element- Lake Road – Alabama 161 kV • Contingent Element –St. Joe - Hawthorn 345 kV • Reason for Violating: Outage in the area along with high MISO wind.

  8. OSGCANBUSDEA • Monitored Element- Osage - Canyon 115 kV • Contingent Element – Bushland – Deaf Smith 230KV • Reason for Violating: High wind in the west.