An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Quarterly Transportation Report2nd Quarter 2012April 17, 2012 Thomas Blaser – Director Department of Transportation

  2. Transportation Headlines Location & Design Public Hearing • Route 28 (Linton Hall Road to Fitzwater Drive) • Wednesday, April 25, 2012 • 7:00 pm to 9:00 pm • Patriot High School 10504 Kettle Run Road Nokesville, VA 20181

  3. University Boulevard PPTA(Prince William Parkway to Sudley Manor Drive) Accomplishments • Hornbaker Road design has been completed and approved by VDOT • University Boulevard design has been approved Issues • R-O-W negotiations with adjacent developments Timeline • Construction activities began in January 2012 on Hornbaker Road with majority of activities starting in the Spring of 2012 • Construction to be complete by December 26, 2013

  4. University Boulevard PPTA(Prince William Parkway to Sudley Manor Drive)

  5. Route 1 – Joplin to Bradys Hill Accomplishments • Project activities and billing are 89% complete • Median work with stamped concrete and grass is 60% complete • Paving is ongoing and is 70% complete Issues • Timing of Inn Street connection Timeline • Construction on-schedule for completion June 2012

  6. Route 28 (Linton Hall Road to Fitzwater Drive) Accomplishments • Design has initiated with survey work underway • Citizen Information Meeting held on October 11, 2011 • Project Value Engineering has been completed • Environmental Assessment Document approved Issues • Construction phasing to expedite completion • Impacts to septic fields and R-O-W acquisition Timeline • Public Hearing scheduled for April 25, 2012 • Anticipated Final Construction Plans – January 2013 • Construction Advertisement for Phase I (Linton Hall Road to Realigned Vint Hill Road) anticipated for Spring 2013 • Phase II to follow contingent on funding availability

  7. Route 28 (Linton Hall Road to Fitzwater Drive)

  8. Fuller Rd./Fuller Heights Rd. (Quantico Marine Corps Base Entrance) Accomplishments • Coordination with Marine Corps Base Quantico (MCBQ) regarding design concerns has been concluded • Environmental Permitting is completed • R-O-W and easement requested from MCBQ on 3/30/12 • R-O-W plans submitted to VDOT for authorization Issues • Maintenance of traffic during construction • Access Management waivers • Flood Plain and CLOMR/LOMR Requirements Timeline • R-O-W authorization from VDOT anticipated by Summer 2012

  9. Fuller Rd./Fuller Heights Rd. (Quantico Marine Corps Base Entrance)

  10. Telegraph Road Commuter Lot Accomplishments • Final grading activities ongoing for Phase I (Commuter Lot) • Temporary SWM activity is complete • Demolition of pavement is complete • Storm sewer pipes are 90% complete Issues • Coordinate with adjacent developers • Utility Relocations • Opening of Phase I Timeline • Lot construction (Phase I) scheduled for completion – August 31, 2012 • Final R-O-W plan approval for road improvements – February 2012 • Construction advertisement for road improvements (Phase II) – May 2012 • Construction for road improvements anticipated to be complete – Summer 2013

  11. Telegraph Road Commuter Lot

  12. Old Bridge Road Pedestrian Improvements (Mohican Road to Dillingham Square) Accomplishments • Design of the project incorporating the VDOT Safety Project is in progress • Project is in coordination with VDOT Safety Project Issues • None Timeline • Construction is anticipated to start Fall 2012

  13. Prince William Parkway (Old Bridge Road to Minnieville Road) Accomplishments • Preliminary Design/Build Plans completed by AMT • Project to be financed through Bond funding and use of State Revenue Sharing funds • RFP advertised – February 2012 Issues • R-O-W Impacts • Utility relocation Timeline • Bid opening on May 23, 2012 • Award Design/Build contract Summer of 2012

  14. Rollins Ford Road Accomplishments • Design for roadway extension has been submitted to VDOT for approval Issues • Project construction will include two phases and two Notice To Proceeds (NTPs) • Improvements at Vint Hill Road to meet current standards • Coordination with Park Project Timeline • Advertisement for construction for roadway extension anticipated for Spring 2012

  15. Route 1 – Dale Blvd. to Featherstone Rd. Accomplishments • Three unsolicited design-build proposals received for the project • Selection committee selected the firm of Lane Construction to move forward with project negotiation Issues • Project Funding • Waterline Construction Timeline • Award of design-build contract – Spring 2012

  16. Minnieville Road – Spriggs Rd. to Rte. 234 Accomplishments • Three unsolicited design-build proposals received for the project Issues • Selection committee rejected all PPTA proposals Timeline • Issuance of RFP for project design – Summer 2012

  17. Mountain Road Improvements (Revenue Sharing/TRIP)(Bear Hollow Trail to Jackson Hollow Road) Accomplishments • Notice to Proceed has been issued to NOVEC • Project has been advertised for construction • R-O-W and easements have been acquired • Environmental Permit issued • Utility Relocation is in progress Issues • None • Maintenance of traffic during construction – Road closure during Summer months Timeline • Utility relocation completion anticipated by end of Spring 2012 with construction to follow • Bid opening on April 13, 2012

  18. Mountain Road Improvements (Revenue Sharing/TRIP)(Bear Hollow Trail to Jackson Hollow Road)

  19. Logmill Road Improvements Accomplishments • Preliminary plan design is in progress • Project Day meeting with VDOT, JMT and PWC DOT held in November 2011 • Meeting held with property owners concerning grade at Parnell Court • Profile to proceed with balanced cut and fill for optimum construction Issues • Possible temporary road closure and management of traffic during construction Timeline • Intermediate Plan submission scheduled for Summer 2012 • Advertisement for construction – Spring 2013 • Construction completion anticipated for Fall 2013

  20. Fuller Heights Rd. Sidewalk –Bethlehem Church Rd. to Potomac Crest Dr. (TRIP) Accomplishments • R-O-W acquisition is completed • Construction by County forces is in progress Issues • Coordination during construction of sewer line • Drainage design affecting adjacent properties • Project Budget Timeline • Construction completion is anticipated in Summer of 2012

  21. Hoadly Road Trail – Spriggs Road to Dale Boulevard (TRIP) Accomplishments • Plans submitted to VDOT • Comments received from VDOT and Development Services are being addressed Issues • R-O-W and easement constraints • Possible design waiver Timeline • Plans expected to be re-submitted to VDOT in April 2012

  22. Gideon Drive Sidewalk – Dale Blvd. to Opitz Blvd. (TRIP) Accomplishments • Notice to Proceed with preliminary design has been issued to RDA • Task Order to RDA has been modified to accommodate use of Federal CMAQ funding on project for construction Issues • R-O-W and easement constraints • Utility Relocations Timeline • Preliminary design scheduled for submission to VDOT – May 2012

  23. Glenkirk Road Sidewalk Accomplishments • County request to administer project approved by VDOT • County/Sate Agreement has been received and funding budgeted and appropriated • Federal design task order has been issued to Dewberry Issues • Expedited construction schedule Timeline • Advertise for construction in Fall 2012

  24. Mine Road @ Van Buren Road Intersection Improvements Accomplishments • County request to administer project approved by VDOT • County/Sate Agreement has been received and funding budgeted and appropriated • Federal design task order has been issued to Dewberry Issues • None Timeline • Advertise for construction in Fall 2012

  25. Panther Pride Drive Sidewalk Accomplishments • County request to administer project approved by VDOT • County/Sate Agreement has been received and funding budgeted and appropriated • Federal design task order has been issued to Dewberry Issues • None Timeline • Advertise for construction in Fall 2012