280 likes | 455 Views
P09454: Design & Testing of Centrifugal Pump Components. MSD II –Managerial Presentation Spring 2009. Design Team:. Rishitha Dias - ISE – Project Manager Kevin Klucher - ME – Lead Engineer John Hayles - ME Reme Meck - ME Ammar Jangbarwala - ME. Project Background:.
E N D
P09454: Design & Testing of Centrifugal Pump Components MSD II –Managerial Presentation Spring 2009
Design Team: • Rishitha Dias - ISE – Project Manager • Kevin Klucher - ME – Lead Engineer • John Hayles - ME • Reme Meck - ME • Ammar Jangbarwala - ME
Project Background: • Project Family: Sustainable Technologies for the Global Marketplace • Project Track: Flow Visualization • Sponsor: Dresser-Rand Corp. • Faculty Guide: Dr. S. Day
Project Deliverable: The goal of the project is to design, build, test and deliver to KGCOE, a centrifugal pump system for particle imaging velocimetry (PIV) studies, which can be used both as a teaching tool for undergraduate students as well as a research tool for graduate and faculty researchers.
Customer Needs: Primary Customers: • Faculty & Graduate Researchers • Undergraduate Instructors Customer Needs / Target Specifications: • Generate Multiple Flows ~ 3 Unique Impeller Designs ~ 2 Unique Diffuser Designs • PIV Compatibility >85% Transmissivity of Pump Components • Lab Teaching Tool < 5 min Component Swap Time > 0.45” Tool Clearance Measureable Flow, Pressure & Power. Parts must withstand a drop from 42”
Inherited Pump System: Sensors & Actuators GUI Close-up view of Pump Housing & Impeller Tank
Design Concept Summary Impeller & Diffuser Riser
Impeller Designs Previous Impeller Design: New Impeller Designs: P09454-102 P09454-103 P09454-104 P09454-105 P09454-106
Impeller Designs Old Impeller Design:
Diffuser Designs P09454-203 P09454-201
Budget: • > 40% of the $6,500 budget remaining • Component Manufacture & Materials costs are dominant.
Schedule:Product development Phase Phase 1 Planning Current Stage of Design Phase 2 Concept Development System Level Design Phase 3 Testing & Refinement Phase 4 MSD I MSD II
Schedule: • Project is on Schedule • Component Manufacture Complete • Pump Assembly Complete • Flow Testing Complete • Documentation Complete
Performance: • Measure Pressure, RPM & Flow • Built into GUI functionality • Control Flow, RPM, Pressure • GUI Controls & Valves • PIV Compatible • Clear Acrylic Components • Characterize Various Flows • 5 Impellers & 2 Diffusers available to generate curves • Interchangeable Components • Assembly/Disassembly averages 3.5 minutes
Test Results • As head rises, the flow decreases, demonstrating basic pump curve relationships. • With the addition of a vaned diffuser, the head generated is increased versus flat ring diffusers.
Discussion • Pump provides 10x the options (impeller and diffuser) with 65% faster component switch time • Head generated is up to 60% greater than previous system benchmarks • Flow rate is not up to maximum theoretical value of 22.3 gpm. However, ~ 25% increase over previous iteration • Diffuser made a large difference in the amount of head generated, up to a 27% increase for the basic 102 impeller • New designs can be rapid prototyped and tested in the test loop within several days based on standard dimensions used for the components