Q & A : Construction Committee Meeting Presentation and discussion on the status update and plans of action pertaining to the $60M Bond, $57M Bond, and other related projects. D11.15.07. Objectives:. Implement and utilize a “Best Practices” approach process in order to:

jerod
Download Presentation

Objectives:

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Q & A : Construction Committee Meeting Presentation and discussion on the status update and plans of action pertaining to the $60M Bond, $57M Bond, and other related projects. D11.15.07

  2. Objectives: • Implement and utilize a “Best Practices” approach process in order to: • Review, discuss, and evaluate facts; • Develop and/or review observations and conclusions; • Develop and/or review available plan(s) of action; • Select and implement a timely plan(s) of action.

  3. $60M Bond 2005 Series (8/29/05)

  4. $60M Bond EstimatedConstruction2005 Series 8/29/05 Original Estimates

  5. $60M Construction Bond2005 Series 8/29/05 Original vs. New Estimates *Rappaport Building was purchased at a cost of $1,922,902.00. ** Nixon Field House was completed at a cost of $2,098,095.81.

  6. $60M Construction Bond 2005 Series Fund Sources/RevenuesAs of 09/30/07

  7. $60M Construction Bond2005 SeriesAs of 09/30/07

  8. $60M Construction Bond2005 SeriesAs of 09/30/07 * Assumes that Admin. Complex requirement was met with procurement of Rappaport Building $1,922,902.00, as well as completion of Nixon Field House $2,098,095.81.

  9. Conclusion • Estimated shortfall of $90,697,471 • Causal and other factors (List is not all inclusive): • Under estimation of original project costs during planning stages; • Inflation (General and Construction related); • Unpredictable substantial increase in construction costs; • Usage of funds of approximately $14M for other needs (e.g. OCRs, Martin WW, Martin PhIII, Cigarroa Scoreboards, Christen MS Academic Wing, Memorial MS Athletic Field, Buenos Aires Land, etc.);

  10. Conclusion (cont.) • Studies were not available to substantiate original allocated bond projections; • There was no scope nor program requirements to support original allocated assessment; • Feasibility cost estimates have now been prepared with support of architects, engineers, administration, and staff; • Estimates are comprised of cost such as professional fees, land, equipment, furniture, relocation, temporary, and other contingency cost;

  11. Conclusion (cont.) • Meetings were held with respective department heads and end users to develop program requirements based on a needs assessment to provide adequate facilities; • The studies were based on new construction rather than renovation of buildings; • Preliminary estimates are based on the proposed construction timeline. Further delays of these projects will generate additional costs; • Consultation was made with bond advisors and a legal opinion has been issued; • Other project needs have impacted the planning and funding of bond program.

  12. Plans of Action • Issuance of New Debt; • Amendment of projects and/or funding; • Other action(s) as determined at workshop; • No action or deferred action.

  13. Option 1 • Issuance of New Debt (Bond Election)

  14. Option 2Amendment of Projects and/or Funding

  15. Option 2 • Prioritized projects as listed on previous page; • Addition of furniture for MHS WW and Gallegos Elem.; and • Deferred/Deleted Projects as listed below: • Transportation Center $ 8,899,987 • Food Services Center $15,745,464 • Fine Arts $18,843,631 • Magnet School $32,179,285 • Administrative Complex * $ 9,000,000 • Contingency, Land, Equipment & Wiring $14,000,000 Total $98,668,367 * Assumes that Admin. Complex requirement was met with procurement of Rappaport Building $1,922,902.00, as well as completion of Nixon Field House $2,098,095.81.

  16. Construction Timeline / Sequence of Projects • The Construction timeline and priority of projects is based on the following factors: • Defined Scope and Needs Assessment • Land Availability • Funding • Design/Architect • Procurement • Logistics • Compliance

  17. Recommendation • After discussion, evaluation, and bond counsel participation of the financial status and construction timelines, the recommendation is as follows: • Approval of Option 2

  18. $57M Bond 2006 Series (09/28/06)

  19. $57M Bond EstimatedConstruction2006 Series 09/28/06 Original Estimates

  20. $57M Construction Bond2006 Series 09/28/06 Original vs. New Estimates *No feasibility study, revised amount for Alter. Ed Campus & 5th MS

  21. $57M Construction Bond2006 Series Fund Sources/RevenuesAs of 09/30/07

  22. $57MConstruction Bond2006 SeriesAs of 09/30/07

  23. $57MConstruction Bond 2006 SeriesAs of 09/30/07

  24. Conclusion • Estimated shortfall of $35,520,976 • Causal and other factors (List is not all inclusive): • Under estimation of original project costs during planning stages; • Inflation (General and Construction related); • Unpredictable substantial increase in construction costs;

  25. Conclusion (cont.) • Studies were not available to substantiate original allocated bond projections; • There was no scope nor program requirements to support original allocated assessment; • Feasibility cost estimates have now been prepared with support of architects, engineers, administration, and staff; • Estimates are comprised of cost such as professional fees, land, equipment, furniture, relocation, temporary, and other contingency cost;

  26. Conclusion (cont.) • Meetings were held with respective department heads and end users to develop program requirements based on a needs assessment to provide adequate facilities; • The studies were based on new construction rather than renovation of buildings; • Preliminary estimates are based on the proposed construction timeline. Further delays of these projects will generate additional costs; • Consultation was made with bond advisors and a legal opinion has been issued; • Other project needs have impacted the planning and funding of bond program.

  27. Plans of Action • Issuance of New Debt; • Amendment of projects and/or funding; • Other action(s) as determined at workshop; • No action or deferred action.

  28. Option 1 • Issuance of New Debt (Bond Election)

  29. Option 2aAmendment of Projects and/or Funding

  30. Option 2a • Prioritized projects as listed on previous page; • Addition of Fire Alarm System and OCR’s; and • Deferred/Deleted Projects as listed below: • Science Lab – Cigarroa HS $ 7,001,977 • Science Lab – Nixon HS $ 8,091,783 • Science Lab – Martin HS $ 7,135,636 • Alternative Education Campus * $10,307,554 • Fifth Middle School * $20,100,000 Total $52,636,950 *No feasibility study, revised amount for Alter. Ed Campus & 5th MS

  31. Option 2bAmendment of Projects and/or Funding

  32. Option 2b • Prioritized projects as listed on previous page; • Addition of Fire Alarm System and OCR’s; and • Deferred/Deleted Projects as listed below: • Early College HS $12,915,697 • Alternative Education Campus * $10,307,554 • Fifth Middle School * $20,100,000 Total $43,323,251 *No feasibility study, revised amount for Alter. Ed Campus & 5th MS

  33. Option 2cAmendment of Projects and/or Funding

  34. Option 2c • Prioritized projects as listed on previous page; and • Deferred/Deleted Projects as listed below: • Science Lab – Cigarroa HS $ 7,001,977 • Science Lab – Nixon HS $ 8,091,783 • Science Lab – Martin HS $ 7,135,636 • Alternative Education Campus * $10,307,554 • Fifth Middle School * $20,100,000 Total $52,636,950 *No feasibility study, revised amount for Alter. Ed Campus & 5th MS

  35. Option 2dAmendment of Projects and/or Funding

  36. Option 2d • Prioritized projects as listed on previous page; and • Deferred/Deleted Projects as listed below: • Early College HS $12,915,697 • Alternative Education Campus * $10,307,554 • Fifth Middle School * $20,100,000 Total $43,323,251 *No feasibility study, revised amount for Alter. Ed Campus & 5th MS

  37. Construction Timeline / Sequence of Projects • The Construction timeline and priority of projects is based on the following factors: • Defined Scope and Needs Assessment • Land Availability • Funding • Design/Architect • Procurement • Logistics • Compliance

  38. Recommendation • After discussion, evaluation, and bond counsel participation of the financial status and construction timelines we are recommending the following: • Approval of Option 2a

  39. Other Related Projects