I 66 Widening Design/Build Project Pardon Our Dust May 8, 2014 6:30 PM

I 66 Widening Design/Build Project Pardon Our Dust May 8, 2014 6:30 PM. The Project Team. Virginia Department of Transportation Shirley Contracting/Dewberry Federal Highway Administration Town of Haymarket. Tonight’s Objective. Provide Project Status Update Overview of the Schedule

jerold
Download Presentation

I 66 Widening Design/Build Project Pardon Our Dust May 8, 2014 6:30 PM

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. I 66 Widening Design/Build Project Pardon Our Dust May 8, 2014 6:30 PM

  2. The Project Team • Virginia Department of Transportation • Shirley Contracting/Dewberry • Federal Highway Administration • Town of Haymarket

  3. Tonight’s Objective • Provide Project Status Update • Overview of the Schedule • 2014 Construction • Answer Your Questions

  4. Project Overview • Project Limits from Route 29 to 1 Mile West of Route 15 • Widen I-66 to 4 lanes each direction • Left Lane will be designated as HOV • Widen WB Off-Ramp to Route 15 to Provide 2nd Left Turn Lane • Reconstruct Old Carolina Road and Catharpin Road Bridges • Construct Noise Barriers

  5. WB Ramp to Route 15 Improvements Add 2nd Left Turn Lane to Route 15

  6. Bridge Reconstruction Catharpin Road Old Carolina Road

  7. Project Schedule • August 2013 Design/Build Contract Awarded • Fall/Winter 2013 Final Design, Obtain Permits • Spring 2014 Begin Construction • August 21, 2016 Construction Complete

  8. Lane Configuration Existing and Stage 1&2

  9. Lane Configuration Stage 3 June 2014 to January 2015

  10. Lane Configuration Stage 4 January 2015 to August 2016

  11. Lane Configuration Ultimate August 2016

  12. Detours During Construction • Old Carolina Rd / Jefferson Street will be CLOSED • between Walter Robinson Ln & Cheyenne Way. • Why: Demo & Reconstruct I66 Overpass • When: Late June 2014 to November 2015 • Detours: via Route 15 or Catharpin Rd

  13. Detours During Construction

  14. Addressing Your Concerns… Regarding Construction • Traffic disruptions will be minimized to the extent possible with daily off-peak lane closures along I-66 and Route 15 Interchange Ramps • A majority of the construction operations will be on weekdays during normal daytime hours, generally 6:00 am to 5:00 pm. • Some work will need to be done at night (bridge demolition, bridge beam erection, deck pours, major drainage construction, paving and striping).

  15. For More Information About Route I66 Widening Project: • Additional Pardon Our Dust meeting will be scheduled prior to major milestones. • http://www.virginiadot.org/projects/northernvirginia/i-66_widening.asp • (this webpage will be updated throughout the project development) • VDOT Contact: christiana.briganti@VDOT.Virginia.gov • (703) 259-2960 • THANK YOU!