1 / 16

TSPLOST Update

TSPLOST Update. Columbus City Council February 25, 2014. COLUMBUS TSPLOST PROJECT LISTING. TSPLOST PROJECTS. Band 1 CY 2013 - 2015. COLUMBUS RIVERWALK. Project Description: The extension of the Riverwalk behind Bibb and City Mills to complete theproject.

jerom
Download Presentation

TSPLOST Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TSPLOST Update Columbus City Council February 25, 2014

  2. COLUMBUS TSPLOST PROJECT LISTING

  3. TSPLOST PROJECTS Band 1 CY 2013 - 2015

  4. COLUMBUS RIVERWALK Project Description: The extension of the Riverwalk behind Bibb and City Mills to complete theproject • Projected Costs: $10,000,000 • PE - $1,000,000 • CST - $9,000,000 • Status: • Notice To Proceed – April 24, 2013 • Hecht Burdeshaw is preparing construction plans • All ROW has been identified. No additional property will be required • Construction is expected to begin by September/October timeframe Riverwalk at Bibb Mills and North Highland Dam Riverwalk at City Mills As of February 20, 2014

  5. INTERCITY EXPRESS BUS PARK-N-RIDE SERVICE Project Description: Construction of three express bus Park-N-Ride locations in Columbus using existing sites. • Projected Costs: $22,400,00 • Costs to include design, maintenance and operation • Budget for these items still to be determined • Status: • Notice To Proceed – April 24, 2013 • Connectics Transportation Group was hired in October 2013 to perform a Public Transit Needs Assessment • Assessment needed to determine how best to serve our citizens • Study includes route analysis, rider surveys • Public meeting to hear citizens needs and concerns on February 27, 2014 • No other activities will begin until study is completed Proposed Trail From Infantry Museum to Levy Road Current METRA Route System As of February 20, 2014

  6. SOUTH LUMPKIN MULTI-USE FACILITY Project Description: A pedestrian/bicycle facility to be built along an abandoned rail road line. This linear greenway corridor is divided by Old Cusseta Road, Victory Drive, and Fort Benning Road Proposed New Trail From Infantry Museum to Cusseta Road • Projected Costs: $3,500,000 • PE – $ 500,000 • CST - $2,500,000 • Status: • Notice To Proceed – September 10, 2013 • Heath & Lineback Engineers are the lead consultants on this project • Public meeting was held on January 16, 2014 • Preliminary design – May 2014 • Final design – November 2014 • Project Bid & Construction – January 2015 • No other activities will begin until study is completed As of February 20, 2014

  7. US 27/CUSTER ROAD INTERCHANGE RECONSTRUCTION/MODIFICATION Project Description: This project will provide permanent public access to the proposed property bounded by US 27 to the south, I-185 to the west, and Cusseta Road to the north and east, which is the western boundary of Fort Benning • Projected Costs: $20,000,000 • PE – $ 1,000,000 • CST - $19,000,000 • Status: • Notice To Proceed – April 19, 2013 • Discussions are still continuing with Ft. Benning officials to obtain approval • Wolverton& Associates have begun preliminary design on project – expect completion by December • Construction projected to begin Spring 2015 Proposed property to be accessed by project As of February 20, 2014

  8. TSPLOST PROJECTS Band 2 CY 2016 - 2019

  9. US 27/CUSTER ROAD INTERCHANGE RECONSTRUCTION/MODIFICATION BUENA VISTA ROAD INTERCHANGE Project Description: The purpose of the project is to reconstruct the interchange of I-185 and Buena Vista Road • Projected Costs: $47,670,000 • ROW - $28,700,000 • PE – GDOT Authorized in 2001 • CST - $18,970,000 • Status: • Notice To Proceed – Will not be authorized by GDOT until 2016 • GDOT has expressed an interest to accelerate this project by authorizing the engineering to begin in 2014 Buena Vista Road Interchange As of February 20, 2014

  10. INTERSECTION IMPROVEMENTS ALONG BUENA VISTA ROAD (Spider Web) Project Description: The project will include road realignments and/or a possible overpass on Buena Vista Road • Projected Costs: $40,000,000 • PE – $ 2,522,522 • ROW - $ 8,649,648 • CST - $ 25,225,225 • UTL - $ 3,603,605 • Status: • Notice To Proceed – Will not be authorized by GDOT until 2016 • City has taken the initiative to fund the preliminary concept and design of this project now • Public hearing on this matter should be scheduled within the next 60 days • GDOT has expressed an interest to accelerate this project by authorizing the engineering to begin in 2014 Spider Web Area As of February 20, 2014

  11. SR 219 PASSING LANES FROM LUTHER LANDING BRIDGE TO HAPPY HOLLOW ROAD (River Road) Project Description: A passing lane will constructed along SR 219 from Luther Road Bridge to Happy Hollow Road • Projected Costs: $17,690,438 • PE – $ 1,597,736 • ROW - $ 403,427 • CST - $ 14,187,438 • UTL - $ 1,501,837 • Status: • Notice To Proceed – Will not be authorized by GDOT until 2016 • This project will eventually be the sole responsibility of GDOT As of February 20, 2014

  12. TSPLOST PROJECTS Band 3 CY 2020 - 2022

  13. CUSSETA/OLD CUSSETA ROAD IMPROVEMENTS Project Description: Project consists of improvements on Cusseta and Old Cusseta Road, from Fort Benning Road to Staunton Drive • Projected Costs: $17,690,438 • ROW - $ 41,402,448 • CST - $ 16,866,964 • Status: • Notice To Proceed – Will not be authorized by GDOT until 2020 As of February 20, 2014

  14. DISCRETIONARY FUNDS YTD Collections = $2,422,548

  15. TSPLOST UPDATE February 25, 2014 QUESTIONS?

More Related