This workshop discusses the current state and evolution of RTM settlement timeline, stakeholder input, and lessons learned. It also addresses concerns, proposes next steps, and explores key questions related to data availability, settlement iteration, and credit risk.
E N D
Next Steps to Reduce the RTM Settlement Timeline COPS Workshop August 29, 2013
Agenda • Level Set - Workshop Objectives • Why are we here? • Current State • Evolution of RTM Settlement timeline • Stakeholder & ERCOT Input • TDSP Process • Lessons learned from 9 to 7 • Concerns & Solutions • Next Steps • What to report to TAC & Board?
Objectives – • Problem Statement • What problem are we trying to solve? • Increase in offer caps as of 6/1/2014 to $7000 and 6/1/2015 $9000 • Why is reducing the timeline part of the solution? • Capture Input from Stakeholders & ERCOT • Risks, Impacts, Challenges & Benefits • Lessons learned • Discuss Options and Address Key Questions • At what point does the risk of generation data availability become a “showstopper” or require a solution? • At what point do we anticipate transitioning from settlement on predominantly TDSP-submitted usage data to predominantly ERCOT-estimated usage data? • At what point is an additional settlement iteration needed in order to mitigate risk associated with waiting until Final Settlement to resolve data availability and accuracy issues? • At what point do we anticipate introduction of credit risk that may outweigh credit benefit?
Cash Clearing Stats on the Current OD+7 Schedule • On an OD+7 timeline, the vast majority of the Operating Days have cash cleared through ERCOT within 13 calendar days from the OD. • For each day removed from the timeline, a corresponding day is removed from the cash clearing timeline
Benchmarking with Other ISOs/RTOs The statement and cash clearing timelines added to this map are approximations for an “apples to apples” comparison Statement T+7B, T+2M Cash Clears ~OD+49* Statement T+4B, ~EOM+120, ~EOM+300 Cash Clears ~OD+12* T+10B, T+20B Cash Clears ~OD+43* Statement T+4 (credit only), T+7, T+14, T+55, T+105 Cash Clears ~OD+21* Statement T+1, EOM+5, ~T+120, ~T+240 Cash Clears ~OD+12* Statement Wkly (T+3 to T+9) Cash Clears ~OD+11* Statement T+7, T+47, T+77, T+137,… Cash Clears ~OD+22* Statement T+3, T+12, T+55,… Cash Clears ~OD+12* Statement T+7, T+59, T+180 Cash Clears ~OD+12* *Cash clearing timeline based on an example day of 6/6/2013. However, non-business days have the effect of creating a range of dates during which this activity can occur. Cash clearing is from OD to payment to the Market Participant.
Advanced Meter Settlement Impacts – July 2013 July 2013: At month end, settling 6.3M ESIIDs using Advanced Meter data. July 2013: 97.0% of the load in ERCOT is settled with 15-min interval data (AMS, Competitive IDR, and NOIE IDR).
ERCOT Wide Load Volumes by Meter Type – INITIAL Settlement – July 2013
Next Steps - • Complete finals for August 2013 before finalizing recommendations? • By October 31 we will have final statements for all Initial days of August 2013 posted & invoiced & cash cleared • Impact of moving data agg to day 6 will be known by each MP • Homework • Outstanding questions or data needs • Draft NPRR for review at subsequent workshop? • Or clearly defined alternatives as options to TAC to get more direction • Schedule another workshop with or in lieu of September COPS meeting • General update to TAC and the BOD in September • May delay if receive different direction from TAC/Board • Stakeholder Process • Continue Weekly webex calls to gather feedback on OD+7 timeline