Next Steps to Reduce the RTM Settlement Timeline COPS Workshop August 29, 2013. Agenda. Level Set - Workshop Objectives Why are we here? Current State Evolution of RTM Settlement timeline Stakeholder & ERCOT Input TDSP Process Lessons learned from 9 to 7 Concerns & Solutions
E N D
Next Steps to Reduce the RTM Settlement Timeline COPS Workshop August 29, 2013
Agenda • Level Set - Workshop Objectives • Why are we here? • Current State • Evolution of RTM Settlement timeline • Stakeholder & ERCOT Input • TDSP Process • Lessons learned from 9 to 7 • Concerns & Solutions • Next Steps • What to report to TAC & Board?
Objectives – • Problem Statement • What problem are we trying to solve? • Increase in offer caps as of 6/1/2014 to $7000 and 6/1/2015 $9000 • Why is reducing the timeline part of the solution? • Capture Input from Stakeholders & ERCOT • Risks, Impacts, Challenges & Benefits • Lessons learned • Discuss Options and Address Key Questions • At what point does the risk of generation data availability become a “showstopper” or require a solution? • At what point do we anticipate transitioning from settlement on predominantly TDSP-submitted usage data to predominantly ERCOT-estimated usage data? • At what point is an additional settlement iteration needed in order to mitigate risk associated with waiting until Final Settlement to resolve data availability and accuracy issues? • At what point do we anticipate introduction of credit risk that may outweigh credit benefit?
Cash Clearing Stats on the Current OD+7 Schedule • On an OD+7 timeline, the vast majority of the Operating Days have cash cleared through ERCOT within 13 calendar days from the OD. • For each day removed from the timeline, a corresponding day is removed from the cash clearing timeline
Benchmarking with Other ISOs/RTOs The statement and cash clearing timelines added to this map are approximations for an “apples to apples” comparison Statement T+7B, T+2M Cash Clears ~OD+49* Statement T+4B, ~EOM+120, ~EOM+300 Cash Clears ~OD+12* T+10B, T+20B Cash Clears ~OD+43* Statement T+4 (credit only), T+7, T+14, T+55, T+105 Cash Clears ~OD+21* Statement T+1, EOM+5, ~T+120, ~T+240 Cash Clears ~OD+12* Statement Wkly (T+3 to T+9) Cash Clears ~OD+11* Statement T+7, T+47, T+77, T+137,… Cash Clears ~OD+22* Statement T+3, T+12, T+55,… Cash Clears ~OD+12* Statement T+7, T+59, T+180 Cash Clears ~OD+12* *Cash clearing timeline based on an example day of 6/6/2013. However, non-business days have the effect of creating a range of dates during which this activity can occur. Cash clearing is from OD to payment to the Market Participant.
Advanced Meter Settlement Impacts – July 2013 July 2013: At month end, settling 6.3M ESIIDs using Advanced Meter data. July 2013: 97.0% of the load in ERCOT is settled with 15-min interval data (AMS, Competitive IDR, and NOIE IDR).
ERCOT Wide Load Volumes by Meter Type – INITIAL Settlement – July 2013
Next Steps - • Complete finals for August 2013 before finalizing recommendations? • By October 31 we will have final statements for all Initial days of August 2013 posted & invoiced & cash cleared • Impact of moving data agg to day 6 will be known by each MP • Homework • Outstanding questions or data needs • Draft NPRR for review at subsequent workshop? • Or clearly defined alternatives as options to TAC to get more direction • Schedule another workshop with or in lieu of September COPS meeting • General update to TAC and the BOD in September • May delay if receive different direction from TAC/Board • Stakeholder Process • Continue Weekly webex calls to gather feedback on OD+7 timeline