160 likes | 305 Views
CTC work packages report. Nuria Catalan Lasheras BE/ RF 28.05.2013. Outline. Timeline and text report Work package list and contacts Warm Magnets Wigglers … Next steps. Timeline. Visual presentation of a work package separated in different tasks BLUE: Paper study Requirements
E N D
CTC work packages report Nuria Catalan Lasheras BE/RF 28.05.2013
Outline • Timeline and text report • Work package list and contacts • Warm Magnets • Wigglers • … • Next steps
Timeline • Visual presentation of a work package separated in different tasks • BLUE: Paper study • Requirements • Design, CDR, TDR • Analysis of measurements and Optimization • GREEN: Production • Procurement of parts • Prototype procurement • Measurement bench construction • Assembly • ORANGE: Tests and measurements • In the lab • In the beam
Milestones and deliverables • BLUE: Drawings, thesis, papers • GREEN: Hardware • ORANGE: Reports and final validation
Disclaimer Work in progress. Lots of corrections still going on in all work packages Time granularity is three months and some milestones are taken from the past. Are they still valid? Some tasks missing. Still on going? Nevertheless allows a quick visualization of the status and comparison between tasks By the end of June, this “photograph” shall be accurate for all past activities Presented in order of accuracy. You can stop me at any time…
Warm Magnets. M. Modena Magnetic measurements missing?
Warm Magnets. M. Modena PCL magnets design?
DR SC Wigglers. P. Ferracin First NbSnmagnets? Results? Is there a report?
Beam transport equipment. M. Barnes Deliverables and milestones for the strip line kicker are missing Actual start of the study? Beam tests where and when? Other tasks described in 2009?
Powering. D. Aguglia Publications mentioned? What about the other tasks in the work package? CERN activities
Survey & alignment. H. Mainaud-Durand Construction of measuring benches should be considered as hardware
Survey & alignment. H. Mainaud-Durand Missing all milestones
Instrumentation. T. Lefevre Lots of info still missing! Should be at least 4 work packages… Reporting is always easier to find from collaborations…
What do we have now An homogeneous way to describe the work packages • Tasks, durations, delays • Main results and decisions to be taken • Collaborations for each task • To come: Interrelations between packages. • Links, pictures? To put the CTC work into value? • What is not in the timeline. Will be in the text • Technological challenge • Start of the art • Resources and budgets
Conclusions Every work package will have 1-4 pages of text introduction explaining the challenges start of the art and a short status. Is this ok? Still to contact controls, RF sources, magnetic measurements What to do with other work packages (OP, civil services, dumps and targets)?