Maxine Danaro Associate Director Finance & Business Services

Maxine Danaro Associate Director Finance & Business Services The Claims January 2003 Canberra Bushfires Mt Stromlo (RSAA) $44m Weston Creek (RSBS) $9m December 04 Theft from the Classics Collection Fine Arts Policy $550,000 (for one item) August 05 Explosion in RSC (Chemistry) $4m

johana
Download Presentation

Maxine Danaro Associate Director Finance & Business Services

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Maxine Danaro Associate Director Finance & Business Services

  2. The Claims January 2003 Canberra Bushfires • Mt Stromlo (RSAA) $44m • Weston Creek (RSBS) $9m December 04 • Theft from the Classics Collection • Fine Arts Policy • $550,000 (for one item) August 05 • Explosion in RSC (Chemistry) $4m • No fatalities • $4 m claim December 05 • Water event – Mouse House • Event agreed • Section 2 loss didn’t get up • 27 Feb 07 Storm event over Canberra • Hail / rain • Claim is ongoing

  3. All Different • Total loss versus partial loss • Single underwriter • Multiple underwriter • Single loss assessor • Multiple loss assessors • Domestic underwriter • International underwriter • Sometimes Claims Manager appointed

  4. 27 February Storm Event • CGU ISR Underwriters • Lumley’s – Vehicles • Separate Fine Arts Policy • Travel policy (VC costs)

  5. The Players • CGU – Underwriters • Crawfords Appointed as the Loss Assessors • Willis was ANU’s broker (from 28 Feb 07) • ANU Appointed Claims Manager – MSM • And a myriad of ‘experts’

  6. Quick Overview • Happened at 10.20 pm on a Tuesday • 100 buildings damaged • 10 – greater than $1m • University closed for 3 working days • Classes resumed on Monday 5 March • Some pictures to set the scene

  7. Where to Start • Claim formally notified at 6.30am on the 28th • Loss assessors travelling to Canberra by 9am • Signed with new brokers by lunchtime 28th • ANU requested advice on Claims Mgt Services • Signed MSM on 1 March

  8. How Did We Manage the Event • Facilities & Service take control • VC overseas (travel policy) • ‘Controller’ – Director F&S • BCP’s existed • Priority was to get teaching back underway • Minimise the impact (therefore minimise the loss)

  9. We Were Lucky • No fatalities • Libraries were open to 11pm so staff still on deck • Primary computer centre stayed operational • Power was cut to many buildings (deliberately) • Early in the semester • Minimal impact on student accommodation (2100 beds) • 2 largest research schools – minimal damage • Major lecture theatres were cleanable

  10. Traded on Existing Relationships • Outsourced cleaning contractors so they helped commandeer more cleaners, more equipment • Staff helped (ANU has a mixture of permanent Facilities staff and contracted staff) • We harnessed the power of all our suppliers • The damage in Canberra was patchy so resources were not needed everywhere • We utilised our previous experience!!

  11. Teachng Resumes & then ….. The claim evolved into 2 components • buildings (we included floors in building) • Damaged equipment But F&BS / F&S worked closely together • 50 business units • Decentralised administration • Insurance function sits in Finance & Business • Insurance – FTE of 1.3 (& 10% of my time) • Not appointed to the claim full time

  12. The Strategty Evolves • Agreed an approach with the loss assessors • Four major project managers agreed to help – budgets, tenders & costing reviews approach • Specialist projects run for mechanicals, flooring, skylights, glasshouses, acousticians, roofing experts • Equipment recovery team of 12-15 bought onto Campus • Equipment thresholds agreed with the loss assessor • Remember = Replaced equipment belongs to the underwriter (therefore storage, disposal procedures required) • F&BS Storm page • http://info.anu.edu.au/fbs/About/_27_Feb_Storm.asp?p=1

  13. Some Stats • Carpets 15650 square metres • Vinyl 8500 square metres • Split Systems 475 split and packaged units damaged (total 750-800) • Chillers 24 condensers damaged in major chiller • Sky lights 84 damaged out of a possible 102 • Fume Cupboards 97 damaged out of a possible 487 • Timber Flooring sports hall, aerobics floor, wshops & gallery • Building 160,000 square metres of damage out of a possible 435,000 • Buildings 100 out of 150 • Landscape everything was ‘pruned’ • Meetings days and days of them Paper/ thousands of emails Invoices = ? thousands

  14. One Major Project School of Music • Significant damage • Significant impact on the UG students • No where else to teach them (no relief from DEST dates) • Major facility – damage done to the acoustic integrity of L. Hall (our 1300 seat concert / graduation/ etc facility) • Five flats for visitors - damaged

  15. School Of Music Continued • 2 Steinway grand piano’s damaged (plus many others) • L. Hall – new roof? Could we fix the acoustics from ‘below’ or did the roof have to come off • Scaffolding project • Chair project • Acoustic engineers • Structural engineers • Then ANU decides to do $6m worth of work at the same time

  16. School of Music Continues • Section 2 loss • July Piano Conference • July & December graduations • ‘the opera’!!

  17. Mechanicals • Size of the job • Difficulty getting labour and parts • Complexity of technical issues • Mild summer 07/08

  18. Insurance / Claims Issues • Very few ‘insurance’ issues • Good policy • We rarely got the policy wording out • On site visits – weekly, then fortnightly, then monthly • Saw the Underwriter on Campus!! • 36 months

  19. The Claim Reserve • $75 million • $58 million • $42 miillion • $35 million!! • Work is still continuing • Impact of reserve on ‘renewal’

  20. Why Not $75 m • ANU always thought about $50m • Our section 2 loss has been much smaller • We have utilised extensively our relationship with our panel contractors • Gone to tender where possible • Some work done by ANU staff • Carpet bought up front & stored on Campus • Not always possible to utilise ‘externals’ or replace people eg Insurance staff time – not charged to the claim – the hidden cost

  21. What Would We Do Different • Insist on a senior ANU employee being formally appointed, full-time as project manager • More forceful on equipment recovery and disposal • More forceful on our 50 business units – see insurance & pass the buck • Just accept that ‘repair’ is more work than a ‘total’ loss • Try to manage the ‘claim fatigue’ better

  22. Post the Storm • Trying to ensure ‘standards’ are complied with for skylights, roofing etc • Continuing our stormwater strategies • Still formatting/ submitting the claim • Still doing carpet, mechancials & glasshouses • L. Hall, in the School of Music re-opens tonight • Living with a poor claims record & the impact on our premiums/ level of cover etc