Reliability Programs at Arizona Public Serivce. Donald Lamontagne Engineering Manager Reliability Analysis and Standards Western Underground Committee Hotel Valley Ho Scottsdale, AZ September 26, 2012. Distribution Reliability Measurements. IEEE 1366 – 2003
E N D
Reliability Programs at Arizona Public Serivce Donald Lamontagne Engineering Manager Reliability Analysis and Standards Western Underground Committee Hotel Valley Ho Scottsdale, AZ September 26, 2012
Distribution Reliability Measurements • IEEE 1366 – 2003 • Momentary/Sustained Threshold defined • System Average Interruption Frequency Index • All Weather • Clear Weather • System Average Interruption Duration Index • Momentary Average Interruption Frequency Index • Customer Average Interruption Duration Index • Major Event Day
Reliability Target Setting • Assumption – Previous maintenance is reflected in future performance • 10 Year Trend • Data uncertainty bands help guide Threshold, Target, Max • Targets have to be set before the close of the year so a level of uncertainty exists
Example for SAIDI DRAFT
Example for SAIFI DRAFT
Example for FO/HMY DRAFT
Planned Maintenance Scoreboard • Purpose • History • Challenges • Target Setting • Reporting • Benefits
2000 vs. 2011 Comparisons • Customer base up 35% (834,136 vs. 1,124,013) • Customer Interruptions down 17% (1,303,264 vs. 1,075,367) • SAIFI down 44% • Customer Hours Interrupted up 11% (1,732,670 vs. 1,919,439) • SAIDI down 30%
2000 vs. 2011 Comparisons • Biggest Improvements in CI and SAIFI • Weather - Storm Related (118,255) (0.11) • Foreign Interference - Dig-ins Customer/Contractor (57,039) (0.05) • Underground Cable (46,318) (0.04) • Weather – Lightning (41,021) (0.04) • Equipment Failure – APS (33,096) (0.03)
2000 vs. 2011 Comparisons • Biggest Improvements in CHI & SAIDI • Weather - Storm Related (207,632 hrs) (11 min) • Foreign Interference - Dig-ins Customer/Contractor (52,980 hrs) (3 min) • Underground Cable (47,373 hrs) (3 min) • Foreign Interference – Vehicles (43,517 hrs) (2 min) • Weather – Lightning (41,976 hrs) (2 min)
Asset Management EHV Efforts (2000 – 2013) • Focus on FC – CH – PP (1963), FC – MK – ELD (1966), and NV – WW (1973) systems • Series Capacitor Banks (13 @ ~ $5.5M each) • Reactors (27 @ ~ $3M each) • Circuit Breakers (~ 50 @ ~ $1M each) • Transformers (10* ~ $3M each) * 7 were WW fire replacements
Asset Management Replacement Focus
Critical Transformer Examples • Cholla 230/69kV #1 – 52 years • Cholla 345/230kV #7 – 51 years • Four Corners 345/230kV #8 – 51 years • Four Corners 230/69/4.16kV #1 & #2 – 45 and 49 years • Saguaro 525/115kV #4 & #7 – 37 years • Cholla 525/345kV Bank #3 & #6 – 33 and 37 years
Asset Management Replacement Focus