160 likes | 180 Views
Discover strategies for managing deviations from design targets in disposal facility operations, including the role of safety cases, monitoring, and corrective actions. Learn about real-life examples and crucial prerequisites for high-quality operations.
E N D
Managing deviations from the Design Target with the Safety Case IAEA GEOSAF II Plenary 2014
Content Walk through of the safety case loop diagram • Role of safety case during construction and operation • Prerequisites for high quality operations (build and Operate) • Role of monitoring, QA/QC and qualification procedures • Assessment of deviations • Examples • Updating the Safety Case
Disposal facility life cycle • At the time of disposal facility operational period the safety case has passed stepwise process on development (concept, siting, preliminary design, ...) • After authorization the disposal facility will in many case be operated for several decades. • The facility is also likely to be extended in several stages with concurrent activities (excavation, waste emplacement, partial closure) • The continuous use of Safety Case and demonstrations that performed activities comply with safety envelope is fundamental for success.
Role of the Safety Case • Discussed in earlier presentations • For disposal facility the important aspects of safety case is that it integrates operational and post-closure safety • Safety case should define requirements that construction and operation shall fulfill (fulfilled as-built initial state “assures” assessed long-term safety) • These requirements define safety envelope which again gives provisions for design target.
Prerequisites for high quality operations • Integrated management system • Systematic process for development and management of requirements • Comprehensive project management procedures • Design specifications and plans that construction and operation must follow • Procedures for constructions and operation activities • Monitoring of safety related key parameters • Demonstration of compliance within design target (DT) • Discussed for example in IAEA GS-R-3 and Safety Guide GS-G-3.4
Monitoring and demonstration of compliance • Discussed in earlier presentation • Monitoring is discussed for example in IAEA draft Safety guide (DS357) • Management system should include detailed procedures for demonstration compliance with design target • Monitoring should focus on parameters that are important for safety and also observable in real disposal facility • Monitoring and QA/QC procedures are a tool for verifying that as-built state is acceptable • Examples • Tolerances of disposal rooms • Waste package testing • Waste acceptance verification • Monitoring of favorable site properties • … In compliance?
In case of deviation from DT (1) • Most likely deviations are found during construction and operation – if not, the management system is not working properly • Deviations should be addressed through predefined procedures • First step in deviation analysis is to assess it safety significance • Analysis may focus on estimation of large enough safety margin or call for more detailed analysis of the effect • Based on the analysis deviation can be approved, documented and closed or it may require corrective actions or rejection product • Deviation management process is discussed in further detail for example in IAEA GS-R-3 (non-conformances and corrective and preventive actions)
In case of deviation from DT (2) • Possible, more safety case related, actions for the implementer based on monitoring results or in case of deviation : • Refine construction or operational procedures to reverse a trend that if left unaddressed could cause the parameter eventually to fall outside of the DT (and potentially outside of the SE); • Commission further research to understand the consequences of the deviation. This may have the effect of expanding the DT and consequently bringing the value into compliance; • Review the safety case to determine whether additional safety features can be claimed thereby compensating for the design deviation. An updated safety envelope could be also envisioned at this stage. • In extremis the deviation may be so severe, so far from the SE that the operator will need to consider whether it is still possible to achieve a satisfactory safety case.
Examples from “real life” • Exceeding excavation damage zone (EDZ) tolerance • Maximum EDZ is given in tunnel technical specification • Depth of EDZ is examined with ground penetrating radar • Continuous EDZ might have effect on post-closure safety as a potential transport route • Possible actions: • In any case assessment of causes for exceeding specification • Approval and documentation of exceeding, if only local • Cutting and plugging of continuous EDZ (engineering solution) • Re-assessment and update of safety case, if continuous EDZ can’t be avoided
Examples from “real life” • Exceeding tunnel profile specification • Theoretical tunnel profile is given in tunnel specification and in design drawings • As-built profile is examined with laser scanning and other measurements • Over excavation has an effect on tunnel backfill emplacement and possibly on post-closure performance • Possible actions: • In any case assessment of causes for exceeding specification • Approval and documentation of exceeding, if not affecting DT when assessed together with backfill performance • Redesign of tunnel backfill and assessment of performance if needed to meet DT
Examples from “real life” • Waste package tested to have too large defects • Waste package specification includes acceptable defect size and type • Larger defect can have an effect on corrosion resistance or mechanical integrity in extreme loading cases (operational and post-closure) • Waste container is a key safety barrier and deviations have always safety implication • Possible actions: • More detailed re-evaluation of the defect size using more accurate methods or detailed sizing of defect • rejection of waste container component or welding that does not meet design specification
Examples from “real life” • Water inflow to tunnel exceeds maximum limit used in safety case • In crystalline bedrock a key target is to maintain favorable site properties • Large water inflow has an effect on hydrological and geochemical features of the whole site (water table drawdown, up coning of deeper groundwater) • Possible actions: • More detailed re-evaluation of the possible change in the site properties • a long-lasting or irreversible change might recall for large re-assessment, change of disposal design or even rejection of site
Updating the Safety Case • Safety case should be updated during disposal facility operation • A comprehensive update will take place according to national approach, but should be done for example in case of • stepwise facility authorization • other facility modification • periodic safety review • relicensing of facility (if for example required by national legislation) • Before closure of the facility • New information from operational period should be integrated into the safety case • Assessment that operation has demonstration that operation (as-built state) has been in compliance with design target and safety envelope • experience (more knowledge from construction, fabrication and emplacement) • Site characterization data • New safety related information (R&D, other facilities, …)