1 / 16

TS4 preparatory meeting 11-12-2012

TS4 preparatory meeting 11-12-2012. TS4 – weeks 51-52-1. Underground access possible in week 51 – as from Monday morning 9:30 Ulli and Philippe will start the RP search at 8:30 Access in weeks 52 & 1 will be restricted (only critical activities) No access in these periods:

jon
Download Presentation

TS4 preparatory meeting 11-12-2012

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TS4 preparatory meeting11-12-2012

  2. TS4 – weeks 51-52-1 • Underground access possiblein week 51 – as from Monday morning 9:30 • Ulli and Philippe will start the RP search at 8:30 • Access in weeks 52 & 1 will be restricted (only critical activities) • No accessin these periods: • Lift maintenance  20th Dec 7:00 AM to 9:00 AM • Evacuation test  28th Dec (whole day) • Lift conformity  3rd Jan (whole day) • Magnets will stay off • Ramp down on Monday 17th at 6:00 or 8:00, depending on LHC program (SL action) • DAQ-DCS-HLT available at all times TS4 preparatory meeting - A.Tauro

  3. TS4 – detector’s activities1/5 TS4 preparatory meeting - A.Tauro

  4. TS4 – detector’s activities 2/5 TS4 preparatory meeting - A.Tauro

  5. TS4 – detector’s activities 3/5 TS4 preparatory meeting - A.Tauro

  6. TS4 – detector’s activities4/5 TS4 preparatory meeting - A.Tauro

  7. TS4 – detector’s activities 5/5 TS4 preparatory meeting - A.Tauro

  8. Wk 51: L3-MNF activities SPD has to access L3 every day for short periods TS preparatory meeting - A.Tauro

  9. TS4 – other activities • TE-VSC: installation and test of the GIS table (crane needed – remove green fences) • Start Monday at 14:00 – will close the central valve • PH-DT (gas group): replace pump of TRD gas system. 2 pumps are currently working in parallel (9’500h and 8’000h of work – limit is 10’000h) • Tue 18th Dec.’12 (tbc)  swap one pump • EN-CV: • Maintenance drainage pump (‘pompe de relevage’) (UX25) • Maintenance P2 chillers (19-21 Dec) • EN-HE: put UX25 crane in operation (reinstall electronics) • EN-HE (Réel-Altéad): installation of anti collision system between PR709 (SX2) and PR774 (UX25) TS4 preparatory meeting - A.Tauro

  10. TS4 – Diesel and SVC tests 1/2 • Diesel test planned on Wednesday 19/12 from 7:00 AM to 7:05 AM • A ~5 minutes cut of: • all offices, meeting rooms, wall outlets, light, coffee machine • all SXL2 • Working Rooms in the ACR • the non UPS part of the detector cooling plants (interlocks triggered) • the gas systems (PLCs stopped, interlocks triggered) • the circulation of iced and mixed water, ventilation • Are NOT affected at P2: • all equipment on UPS • all racks in CR and UX • For info: this is CERN-wide, this affects also all offices and labs in Meyrin All gas systems stopped on Wed before 7:00 What about Detector Cooling? TS4 preparatory meeting - A.Tauro

  11. TS4 – Diesel and SVC tests 2/2 • 18kVcompensator (‘filter’) test, planned on Wednesday 19/12 starting at 09:30 AM • Possible perturbations on all networks, including rack power. Only exception: UPS power • Advise to ramp down all HV and if possible LV (possible trips of CAEN and ISEG) • Central systems availability during these two tests: • DAQ: • Will shutdown consoles in WRs and majority of CR1 on Tuesday evening (t.b.c by RC) • HLT: • Might shutdown part of CR2 (t.b.c. if and when) • DCS, safety systems: • Not affected (but DCS maintenance in the shadow) TS4 preparatory meeting - A.Tauro

  12. TS4 – DCS • Bottom line: don’t touch! • But please make your backups • Monday 17/12 (morning) • ‘Usual’ DataBase updates, normally transparent • Possible DB shutdown for repowering • Wednesday 19/12 (morning) • In the shadow of the 18kV filter tests • Reboot of DCS cluster • Make sure you save your work (latest Wed. 19 at 09:00) TS4 preparatory meeting - A.Tauro

  13. TS4 – End-Of-Year closure • Weeks 52 & 1 • Different from last years • ALICE remains ‘powered’ • 24/24 shift coverage (DCS and DAQ) • Re-enforced on-call for online systems • Immediate actions are possible by shifters • Make sure you provide clear and precise instructions! • As other years: daily inspection tours in CRs and UX • To spot the obvious • ‘Usual suspects’ will be contacted soon TS4 preparatory meeting - A.Tauro

  14. TS4 – status of gas & cooling systems CV and Gas piquet services available at all times TS4 preparatory meeting - A.Tauro

  15. Lifts • AS703 (UX25) – stopped on Jan.3rd • AS715 (CRs) – stopped on Jan 4th TS4 preparatory meeting - A.Tauro

  16. Visits • VIP visit by The Research Council of Norway on Tuesday 8th Jan 2013 • 15:10 Transport to LHC Point 2, building 2285 • 15:25 Visit ALICE surface permanent exhibition (P. Giubellino and Norwegian Colleagues) • 15:50 Walk to building 2255 • 15:55 Don helmets at the entrance to the PM25 lift and descend • 16:00 Opportunity to view the tunnel at Point 2, UJ26 (P. Giubellino and Norwegian colleagues) • 16:15 Visit ALICE underground experimental area (P. Giubellino and Norwegian colleagues) • 16:35 Back to surface TS4 preparatory meeting - A.Tauro

More Related