TS3 preparatory meeting 14/9/2012

TS3 preparatory meeting 14/9/2012. TS3: 17-21/9 2012. TS3. Wk 38: Monday 17 th to Friday 21 st September Ramp down magnets (SL): between Mon 6:00 – 8:30 (latest) RP search (Arturo and Philippe?): Mon 8:30 – 9:15 Access starts Mon at 9:15 No access UX25 during the following periods:

faith
Download Presentation

TS3 preparatory meeting 14/9/2012

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TS3 preparatory meeting14/9/2012 TS3: 17-21/9 2012

  2. TS3 • Wk 38: Monday 17th to Friday 21stSeptember • Ramp down magnets (SL): between Mon 6:00 – 8:30 (latest) • RP search (Arturo and Philippe?): Mon 8:30 – 9:15 • Access starts Mon at 9:15 • No access UX25 during the following periods: • Thursday 6:30 AM to 9:30 AM: monthly maintenance cavern lift (AS703) • Please note that the CR lift will be maintained on Thursday between 9:30 AM and 12:30 AM – access to CRs via stairs • Access stops Friday at 16:00 TS preparatory meeting - A.Tauro

  3. Detector activities 1/3 TS preparatory meeting - A.Tauro

  4. Detector activities 2/3 TS preparatory meeting - A.Tauro

  5. Detector activities 3/3 TS preparatory meeting - A.Tauro

  6. Other activities TS preparatory meeting - A.Tauro

  7. Detector cooling Activities Additional jobs: Study for replace the tanks of TRD & TPC Feec, and check the possibility to use the mixed water on SSD/SDD S.Roussee

  8. Watcher schedule TS preparatory meeting - A.Tauro

  9. DCS Main activities / perturbations: • Monday 17.09 PM • Database maintenance (transparent) • Tuesday 18.09 • 09h00: network intervention by IT on router serving devices in cavern, side C • 30 min ‘blackout’ in worst case, users have been warned with details of intervention by mail • Standard maintenance of DCS cluster, might need reboot of cluster • Maintenance central systems (backups etc.) - several short interruptions, might have impact on central running • Shut down machines in old cluster that are not required for operation • Change/repair a few PCs; some tuning of PVSS projects - will be coordinated directly with the experts concerned. • Detectors will receive instructions for cleanup and backup of their projects • Propose, as usual, full functional test with all detectors on Friday (supersafe-safe-ready-safe-supersafe cycle). TS preparatory meeting - A.Tauro Andre

  10. TC & P2tech • LS1 preparation: • SAA3 • DCal cabling (EN-MEF) • New visitor’s platform • Beampipe removal (TE-VSC) • HMPID removal • TOF and TRD services BBF • Conflict YP with TPC services • ? Trappe ADC • PlancherBois cote I C et O C a remplacer par caillebottis • ? Plancherbois cote O A a remplacer par caillebottis • ? Demontagechevron surpoutremuons • ? Demontagebois dessous MCTS cote I et O • ? Demontagebois sur tubes cooling cote I A • ? Demontageanciensysteme detection incendie • Beam pipe protection • ? Installation cartouche resine CV dans le SD • ? Grillage zonne C Rack muontacker a nettoyer TS preparatory meeting - A.Tauro

  11. Visits • Tbc: Mr. Veltman, (Nobel prize, member of SPC) – Tue • Insurance company: Thu-Fri TS preparatory meeting - A.Tauro

  12. AOB • A new ALICE Confined Space training session will take place next Tuesday (18th September 2012) • Pls contact Fernando TS preparatory meeting - A.Tauro