An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 2011-12 winter shutdown preparatory meeting A.Tauro 04-11-2011 ALICE 2011-12 winter shutdown schedule - A.Tauro

  2. V0.1 2011-12 winter shutdown • Shielding TRD Shielding EMC Close L3 Open L3 TRD infrastructure EMC infrastructure Beam off: Dec 8th at 6:00 AM Beam on: Mar 7th at 18:00 PM CERN closure: 22/12 to 4/1 included ALICE 2011-12 winter shutdown schedule - A.Tauro

  3. UX25 access restrictions Close L3 Open L3 Access restrictions: Removal/installation of shielding (restriction includes RB24 triplets) • PX24 blocks: no access CR5 and UX25 • PX24 beams (35t): no access CR1-5, Expo, and UX-25 • All other blocks: no access to UX-25 (or 1-2 teams max, not on A-side) TRD insertion: no access to MNF AUG test (Arrêt Urgence General – General Emergency Stop) – no access UX25 DSO test (Department Safety Officer) – no access UX25 No access SX2 during manipulation of blocks in SX2 (except ACR and WRs) ALICE 2011-12 winter shutdown schedule - A.Tauro

  4. L3 and MNF access restrictions Close L3 Open L3 • Wks 49-50 and 7: access in normal hours (e.g. TPC) to be coordinated with TC • Wks 1-2: no access inside L3 during TRD SMs insertion • When moving from low-beta to insertion platform: no access to MNF • When inserting the module: no access L3 and MNF • Watcher needed in wks 49-50 and from wk 6 onwards ALICE 2011-12 winter shutdown schedule - A.Tauro

  5. TE-VSC • 8th and 9th Dec: close MNF valve and venting central beampipe • Feb 1st– 23rd: pump down central beampipe ALICE 2011-12 winter shutdown schedule - A.Tauro

  6. GS-ASE • Week 52: evacuation test • Nothing foreseen on PAD/MAD ALICE 2011-12 winter shutdown schedule - A.Tauro

  7. EN-CV-OP – Dec • 8th Dec: adjustment flow of chilled-water in the cavern • Will affect all cooling plants • Keep as many detectors on (24h), in order to check that regulation works (EN-CV-DC side) • Week 50: rinsing of mixed water in UX25 cavern (Philippe) • Refilling in parallel  will not affect ALICE cooling • End wk 50 (16th Dec): test of Dipole flooding alarm • Need access to Dipole (Philippe) ALICE 2011-12 winter shutdown schedule - A.Tauro

  8. EN-CV-OP – Jan/Feb • Thu 5th and Fri 6th Jan:maintenance PMD-MTG-MTK ventilation units • Fri 6th Jan: stop chilled water (SU2) • Therefore stop mixed water (cavern, CRs) • Switch tap water into CRs • Week 2: • Cleaning cooling towers (Mon to Thu) • Maintenance L3 injection and UX25 extraction/injection units. Test of alarms • Modification of chilled water pipe for L3 jacket (Mon) • Maintenance mixed water pumps PX24 (Mon-Wed) and UW25 (Wed-Thu) • Preparation services new ITS dehumidifier • Consolidation of automatic switchover to tap water into CRs • Week 3: • Restart chilled & mixed water (around Wed, tbc) • Maintenance L3 extraction unit. Test of alarms • Maintenance ITS (old) ventilator in CR5 • Maintenance ventilation unit SG2 (Mon-Tue) ALICE 2011-12 winter shutdown schedule - A.Tauro

  9. EN-CV-OP – pending • Repair leak FB pipe: 1 day (compensatory measures tbd) • Removal unused FB pipe (I-side). 1 day (need nacelle) ALICE 2011-12 winter shutdown schedule - A.Tauro

  10. EN-EL • Week 49 or 50 (tbd): • Test general secours: stop general services for 10’ • To be coordinated with VAC team (to not disturb BP venting) • 17/12: Test auto-transfert: • 1.5 days to configure + 1 day test • No impact on experiments • Consolidation 48V network (after incident 11th Jan 2011) • 1 day no access to UX25 • Saturday 7th Jan (tbc) • Thu 12th Jan (tbc): maintenance power transformers: • Will cut EXD1/2X for 3h  cut power to CRs (normal network) • Will cut ITS ventilator and HMPID rack in CR5 • Test AUG P2: Fri Jan 13th – No access UX25 • Major electrical perturbation affecting P2 for whole day • Maintenance power transformer EMT306/2X. Wed 25th Jan • Will stop UX25 air extraction and injection (4h) – impact on access to be seen (Fernando) ALICE 2011-12 winter shutdown schedule - A.Tauro

  11. EN-CV-BE • New ITS dehumidifier unit in SX2 • Installation of air duct (SPIE) from SX2 to CR5 • Connection to chilled water (Iniziative) ALICE 2011-12 winter shutdown schedule - A.Tauro

  12. EN-CV-DC • RP sampling: Dec 8th • SDD-SSD. Replacement pump: plant stopped 1 day on Dec 16th • TOF-PHOS-EMC-SPD. Replacement flowmeter + fix leak: plant stopped 1 day between Dec 19th and 21st • TOF-PHOS-EMC-SPD. Installation PHOS circulator + periodic maintenance: plant stopped from 5th to 12th Jan • SPD. Periodic maintenance + put entire plant on UPS: plant stopped 1 day on Jan 6th • TRD. Periodic maintenance + preventive replacement pump: plant stopped 2 days on Jan 16th and 17thAsked to be anticipated to week 2 • TPC. Periodic maintenance + preventive replacement pump + include heaters in supervision: pant stopped from 18th to 20th Jan • HMPID. Periodic maintenance + preventive replacement pump + level transmitter: plant stopped 2 days on Jan 23rd and 24th • TPC RR. Periodic maintenance + install new filters: plant stopped from Jan 25th to Feb 2nd • SDD-SSD. Periodic maintenance + calibration safety valves (tbc): plant stopped from 3rd to 7th Feb ALICE 2011-12 winter shutdown schedule - A.Tauro

  13. BE-ABP-SU (survey) • With L3 doors open, requiring one full day before Xmas (preferably on Sat w50): • Zero measurement (SF, TPC feet, MNF valve, MNF) • Low Beta network update • C-side photogrammetry (EMCal) • After each TRD insertion, requiring 2h inside MNF : • MNF valve and MNF, requiring 2h inside MNF • At the end of TRD and EMCal, requiring three full days with both doors open: • TRD modules, CAL frame photogrammetry, MNF valve, MNF, SF deformation, TPC feet • Muon ST2 survey needed ALICE 2011-12 winter shutdown schedule - A.Tauro

  14. DAQ-DCS • DAQ shutdown 21st Dec mid-day • DAQ start after cooling and power interventions, end wk 3 • Arrangements for individual LDCs can be organized (send a mail to alice-datesupport@cern.ch) • DCS: keep running during Christmas • Replace PCs weeks 1-2-3-4 • Replacement CR3 racks and removal air conditioning CR2-3-4 • From week 4 ALICE 2011-12 winter shutdown schedule - A.Tauro

  15. TPC • Take out capacitors ALICE 2011-12 winter shutdown schedule - A.Tauro

  16. TPC laser • Annual laser maintenance, 1-2 days. Needs normal power and cooling • Open mirror box below TPC sector A13 (bottom below TPC endplate) and possibly replace camera or mirror. 1-2 days. I want to do this because a weak picture from this mirror/camera makes C-side alignment difficult. Best done with L3 doors open. I believe access between the TOF and TPC should be OK. I need to be able to run the laser, so we need to mount the long laser pipe temporarily after opening of L3 doors. ALICE 2011-12 winter shutdown schedule - A.Tauro

  17. PHOS • As from Dec 8th (PM): • Fix condensation problem on pipes and on top of detector • New redundant power supply for crystal cooling unit • Flowmeter crystal cooling unit (tbc) • 2 new T sensors inside L3 • Replace RCU_0 in module_3 • Connect crystal plant and LVPS to FB water during cooling stoppage: • E.g. on Jan 5th ALICE 2011-12 winter shutdown schedule - A.Tauro

  18. MTK • Replacement of chambers with spare ones • Checking Bus - patch and other Electrical Connections • Minor mechanical corrections and adjustments • Possible changes in CROCUS, if any • We shall need electrical meters, tools, light, laptop and a small ladder inside the FASS during our work. Mamu will meet you after 12th november, and then a detailed ADI [with dates and names of persons] will be submitted for approval ALICE 2011-12 winter shutdown schedule - A.Tauro

  19. MTG • Front-end Electronics: maintenance (spare installation mostly) • 1 week (including validation tests). Nacelle needed • Survey of 2 half-planes (MT12-IN and MT12-OUT) including measurements withtheodolite and photogrammetry, survey of the other 6 half-planes with only theodolite measurements • 1 week. Nacelle needed • General check of gas leakage to be performed after all the other activities • 1 week. Nacelle needed • Tests in-situ for speeding up the configuration of the Regional electronics • 2 days ALICE 2011-12 winter shutdown schedule - A.Tauro

  20. ZDC • Move detectors by 1.36m towards IP to solve the problem of collimator shadow ALICE 2011-12 winter shutdown schedule - A.Tauro

  21. --- ALICE 2011-12 winter shutdown schedule - A.Tauro

  22. Status of gas systemsduring Christmas period • MTR Ar backup • MCH  CO2 backup • PMD  Arbackup • TOF  C2H2F4 backup ? • TRD  On. Will needabout 40 m3 of CO2 for flushing 3 new TRD SMs • TPC  On • PHO  N2 flushing • HMP  Arbackup inletflushing ALICE 2011-12 winter shutdown schedule - A.Tauro

  23. Other activities • Release all TOF crates supports and Decoupling TPC-Space-Frame • Disconnect/reconnect SPD pipes • Modification BBF (EMCal access) • Install C-side ladder + trap • Picture ALICE (A.Saba). End of Jan - beginning of Feb ALICE 2011-12 winter shutdown schedule - A.Tauro

  24. Visits • Group of Italian students (42 students + 4 teachers) • 19th Jan (tbc). Contact: C.Bortolin ALICE 2011-12 winter shutdown schedule - A.Tauro

  25. AOB • P2 shuttle to be prolonged till Fri 16th Dec ALICE 2011-12 winter shutdown schedule - A.Tauro