An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MANAGEMENT REVIEW PHOENIX AZ BRANCH 711 JULY 2011

  2. MANAGEMENT REVIEW • Action item request JUNE 2011 • Sergio Rosas/ Daniel Bailey • Need action plan for returned pipe and where to stage also need location map on pipe yard to be posted on fork lift and yard quality board • Target date - July 29 2011 • Yard map finished Sergio Rosas to approve yard map to be posted by Daniel B at locations, action plan still in process of being completed. • ACTION ITEMS FOR JULY 2011 • Daniel bailey • Need water line run thru out warehouse to feed new eye wash stations • TARGET DATE - AUGUST 31 2011 • RESULTS OF AUDITS - ZERO IN JULY

  3. MANAGEMENT REVIEW • Customer feedback • Incident reports customer • 1.C-711-110, CHUBB – Product marked incorrectly (Danny Garcia) • 2.C-711-109, DRRS Plumbing- wrong quantity shipped ,under (Danny Garcia) • 3.C-711-108,FOOTHILLS-Pricing Error (Danny Garcia) 4. C-711-107,FOOTHILLS-Pricing error (Danny Garcia) 5. C-711-106, FOOTHILLS- Pricing error (Danny Garcia) 6.C-711-105, GUARDIAN FIRE- Pricing error (Joe Balestreri) SURVEYS: we received 11 back (see following pages)

  4. MANAGEMENT REVIEW • SUPPLIER PERFORMANCE & CONFORMITY • 1.S-711-016,VICTAULIC-Wrong quantity shipped under (Sergio Rosas) • 2. S-711-015,VICTAULIC –Incorrect material shipped (Danny Garcia) • 3.S-711-014,SPEARS-Incorrect material shipped • INTERNAL INCIDENT REPORTS • 1.I-711-041,Management- Misc. order related error (Danny Garcia)

  5. OVERVIEW OF MEASURABLE OBJECTIVES

  6. MANAGEMENT REVIEW • Overview of key performance indicators • SUPPLIERS: • • 1. COMPLIANCE TO AML = 100% • • 2.Suplier nonconformance's-three to report in July • • 3. Product inspection- we have had no incidents with our suppliers products In July turned in. • • 4. Suppliers on time deliveries 100% in June. • • CUSTOMER: • • 1.0n-time delivery rate= 91% • 2.Customer feedback (incident reports) total of six incident reports. • • 3. customer surveys – 11 turned in • • 4. total credits for the month of June 28 • " Internal performance: • • BPR=92.9% • • Tax discrepancy -ok at this time • • Freight billing -within limits • • Repair on equipment-F-550 TOTAL $ 2574.25. Forklift fabhop$ 345.00 • • Days of inventory on hand 35 • • Dead inventory on hand 3.1% • " may zero injuries • II Auto/truck incidents-zero to report • " Safety inspection-up to date no incidents to report • • Training on associates-Steven Blaisfork-lift training needed

  7. MANAGEMENT REVIEW • Overview of corrective actions/incidents reports • July 2011 • Corrective action reports –zero to report • Customer incidents- 6 • Supplier incidents-3 • Internal incidents- 1

  8. MANAGEMENT REVIEW • Preventive actions –zero turned in • Training &resource needs- fork lift training for Steve blais • Changes impacting quality management system (changes in business) none at this time.