Berkeley County Title II Jericho Horse Trailhead and Trails

Berkeley County Title II Jericho Horse Trailhead and Trails. Status Report. Title II Project Submission Form. Project Goals and Objectives. Project Description. Over the past several years the Jericho Horse Trail has experienced an exponential increase in equestrian trail use.

josef
Download Presentation

Berkeley County Title II Jericho Horse Trailhead and Trails

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Berkeley County Title II Jericho Horse Trailhead and Trails Status Report

  2. Title II Project Submission Form Project Goals and Objectives Project Description • Over the past several years the Jericho Horse Trail has experienced an exponential increase in equestrian trail use. • The increase use, along with other trail uses has resulted in accelerated trail degradation and resource damage. • Proposing on improving 1,565’ of the trail head road and the existing parking • Kiosk on Jericho trail road • Install a Geoblock system on 1088’ of the rail to repair damages of equine traffic on wet soils and adequately support and dissipate the design loads over highly impacted areas preventing future trail degradation.

  3. Project Cost Analysis Worksheet

  4. Jericho Horse Trailhead Site Plan

  5. Jericho Horse TrailHead Kiosk

  6. Jericho Horse Trailhead Geoblock

  7. The Agreement • Agreement number 12-PA-11081209-009 • Funds Allocated $40,000 • Expiration Date September 30, 2013 • Signed by Dan Davis July 5, 2012 • Signed by Paul Bradley July 11, 2012 • Signed by Velma Harris April 12, 2012

  8. Modification of Agreement • Additional Funds Allocated $25,000 • Expiration Date September 30, 2014 • Signed by Dan Davis September 26, 2013 • Signed by Donald Walker for John Lint September 26, 2013 • Signed by Robin StidhamSeptember 23, 2013

  9. Total funds Allocated to Jericho Horse Trail Improvements $65,000

  10. $44,206 $45,796 Completed Portions • Jericho Horse Trailhead • Kiosk • $1,000 • Bridge Site #1 triple pipe system (to be invoiced) • $590.00 Remaining Balance $19,204 Total

  11. TrailHead

  12. Trailhead

  13. Horse TrailImprovements

  14. Kiosk

  15. Completed

  16. Bridge #1