50 likes | 58 Views
This update highlights the milestones achieved in the RSVP project, including two fall milestones and one additional milestone. It also discusses the manpower levels, priorities, and lessons learned in various areas such as RHIC machine and experiment, E-Cooling R&D, EBIS, and RSVP. The update emphasizes the need for a better distinction for EE's and addresses the large difference between the actual manpower and the peak levels. Overall, the milestones have been met, and the project is peaking in ~07.
E N D
RSVP schedule update (We’re almost there)
Setting RSVP manpower levels • Priorities • RHIC machine & Experiment • E- Cooling R&D • EBIS • RSVP
Lessons Learned • In general, milestones were met • We’re peaking in ~07 • Actual manpower vs. peak – large difference • Some group’s did not use their resource labor • We need better distinction for EE’s