HBD: Update and Schedule

Status update and construction schedule for full-scale prototype, gas purity and window configuration studies, and goals for light source testing.

descobar
Download Presentation

HBD: Update and Schedule

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HBD: Update and Schedule Itzhak Tserruya DC Meeting, BNL, April 13, 2005 • Outline: • Full scale prototype status • Light source test • Construction Schedule

  2. Full-scale prototype • Construction completed: • no major problem with construction • procedure or with jigs • ready to go for final design • Presently studying gas purity and • window configuration. • Only inner window glued. • Outer window attached with masking tape.

  3. Full-scale prototype • 200 l/h N2 flushing • Single window 50 micron thick • is not enough • Can reach less than 10 ppm water • within couple of weeks. • need a few weeks to complete the • window studies and decide on • configuration: • - single window of ~100  thickness • - 2x50  window without N2 flushing • - 2x50  window with N2 flushing

  4. Acceptance || ≤ 0.45  = 135o || ≤ 0.36  = 104o

  5. Light source test GOAL: direct measurement of N0. • Trigger counters installed and aligned. • DAQ OK • Detector vessel, radiator and detector module with CsI photocatode sent from WI to BNL. • CsI measured at BNL and found consistent with measurement at WI • Gas system and transmission through radiator • Urgently need of glove box for detector assembly

  6. Schedule: 1. Detector construction • Goal: Detector ready for Run-6. • Working hypothesis: Run-6 is delayed, starts Jan 2006. • HBD construction: A. WI: - Detector and jigs design: 2m start May 1st end June - Vessel construction: 3m start June 1st end August. - Framing and pretest of GEM foils: schedule dictated by foil delivery from CERN scheduled to start May 1st @ 30 foils/month  assume total delivery time of 4m. Work start June 1st  end September. Shipping to SBU start July 1st  end October. B. SBU: - Set-up of assembly and test facility should be completed by July 1st. - CsI evaporation and module test proceed in parallel in assembly line fashion. Work start July 15  15 November. - Final detector assembly and test November – December. - Full detector ready for installation Jan. 2006. Critical items: - freeze acceptance and GEM size - freeze design and produce motherboards

  7. Schedule: 2. Electronics Pre-amplifier production: - First batch of 200 pre-amps already produced - Production start July, complete in 1-2 months FEM production: - FEM prototype ready end of May 3m test end August - FEM production: begin September 2005  February 2006 - FEM test and installation Schedule: 3. Gas, monitor, infrastructure Gas system: - Construction start after Run-5, complete in 2 months Monitoring systems: - 4m delivery time, ready in September Infrastructure (gas pipe, HV, LV): - start after Run-5