NGAO System Design Phase Management Report - Replan

NGAO System Design Phase Management Report - Replan. NGAO Meeting #6 Peter Wizinowich April 25, 2007. Presentation Sequence. Review of SEMP Status Review of Replan Budget Next Steps. SEMP Status. SEMP Tracking.

jovita
Download Presentation

NGAO System Design Phase Management Report - Replan

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NGAO System Design PhaseManagement Report - Replan NGAO Meeting #6 Peter Wizinowich April 25, 2007

  2. Presentation Sequence • Review of SEMP Status • Review of Replan • Budget • Next Steps

  3. SEMP Status

  4. SEMP Tracking • Tracked (Excel) version of the plan posted at http://www.oir.caltech.edu/twiki_oir/pub/Keck/NGAO/SystemDesignPhasePlanning/NGAO_SD_schedule_v20_tracked_final.xls • Excel version highlights what’s complete, what’s late, what’s due within next month & status of work scope planning sheets.

  5. SEMP Summary 1 • WBS 1. SD Phase Management • On-schedule, except for replan (~ 1 month late) • WBS 2.1. Science Requirements • 1 work scope planning sheet approved. No others submitted. • All 13 science cases scheduled for completion by end of April. None completed. • Version 1 of Science Case Requirements complete. Version 2 due in Mar/07 • WBS 2.2-2.3. System Requirements Document • 1 planning sheet approved, 2 late. • Version 1 complete. Version 2 due in March. Need more feedback, especially on science operations requirements. • Version 1&2 of traceability matrix late.

  6. SEMP Summary 2 • WBS 3.1.1. Performance Budgets • 8 planning sheets approved, 1 submitted, 5 late. • Model assumptions. 3 complete & 1 on schedule. • Model/tool validation. 3 complete & 2 late. • Performance budgets. 1 complete, 6 late (2 others due later). • Version 1 of summary late. • WBS 3.1.2. Trade Studies (29 total) • 12 planning sheets approved, 1 needs changes, 11 late. • 9 complete, 1 cancelled & 15 late. • WBS 3.1.3. System Architecture. • Version 1 should have started, but hasn’t. • WBS 3.4. Science Operations • 2 WBS elements should have been started pre-March, but haven’t & another 5 should have started in Mar. • WBS 3.5 Science Instruments • Only Interferometer started. 4 others should have been started & 1 is late. • WBS 4 SEMP • No significant work planned yet

  7. SEMPMilestonesStatus

  8. Meeting Tracking • The tracked version of the action items from each meeting are posted near the top of the meeting page • Meeting 2 http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/061114_CIT_NGAO_Meeting_2 • Meeting 3 http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/061213_Remote_NGAO_Meeting_3 • Meeting 4 http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/070122_NGAO_Meeting_4 • Meeting 5 http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/070307_Remote_NGAO_Meeting_5 • The bulk of the action items are incomplete • Remember to look at these action items for action items on your presentation (that should be incorporated in the final KAON). • The minutes & action items from the EC meetings are posted at http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/SystemDesignPhasePlanning

  9. Posted KAONs • 415 TMT site monitoring data (restricted access) • 416 Atmospheric sodium density from Keck LGS photometry • 417 Sodium abundance data from MAUI Mesosphere • 419 Simple models for the prediction of Na LGS brightness & comparison to measured returns from the Gemini & Keck lasers • 420 Accessing the MK TMT seeing & weather data • 427 Variable vs fixed LGS asterism • 428 Implications & requirements for interferometry with NGAO • 429 LGS asterism geometry & size • 452 MOAO vs MCAO trade study report • 455 Science Case Requirements Document v1.0 • 456 System Requirements Document v1.1 • 459 NGAO System Design Phase Report #1 • 461 Wavefront error budget predictions & measured performance for current & upgraded Keck AO • 462 Keck AO upgrade trade study • 463 Lessons learned on LGS operations: weather impact, efficiency & science ops model • 465 NGAO LGS wavefront sensor: Type & number of subapertures trade study • 466 Computer simulations of AO PSFs for NGAO • 468 An algorithm for reconstruction of Keck Telescope segment figure errors • 470 Keck NGAO sky coverage modeling • 472 GLAO for non-NGAO Instruments • 473 NGAO System Design Phase Report #2 • 474 AO Photometry for NGAO • 475 Tomography codes comparison & validation for NGAO • 476 Observing Models trade study

  10. Reasons for Replan • Significantly behind schedule • Behind on earned value: 29% of labor & dollars spent, but plan only 24% complete • Planned opportunity (scheduled in SEMP) to revisit plan approach, priorities, tasks, personnel, dictionary definitions, etc. • We also need to improve how we are managing this project • Schedule and budget are tools in accomplishing the project

  11. Replan http://www.oir.caltech.edu/twiki_oir/pub/Keck/NGAO/SystemDesignPhasePlanning/NGAO_SD_schedule_v24.mpp

  12. System Requirements Replan

  13. Changes made in Replan • Excel summary of MS Project changes between versions 20 & 24 posted at http://www.oir.caltech.edu/twiki_oir/pub/Keck/NGAO/SystemDesignPhasePlanning/NGAO_SD_schedule_v24.xls • Highlights what’s changed.

  14. ReplanMilestones(changes in bold)

  15. Replan

  16. Budget Reduction in replan labor largely due to removing 1230h of students

  17. Next Steps • Complete Replan with Team’s input • Determine how to proceed with System Architecture • New & revised WBS dictionary definitions • Improved management strategies • More focused team • Redo team meeting goals • Complete the following items in May: • SCRD & SRD v2 • FRD v0 & Science Instruments FRD v1 • Performance budgets summary • Trade Studies • Define Candidate Subsystems + Remember to do work scope planning sheets for new tasks