An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NGAO ManagementUpdate Peter Wizinowich NGAO Meeting #11 November 5, 2007

  2. Project Reports • 4th & 5th reports submitted to Directors on 9/19 & 11/2 http://www.oir.caltech.edu/twiki_oir/bin/view.cgi/Keck/NGAO/SystemDesignPhasePlanning • Emphasis during this report period has been on: • System architecture evaluation & selection (June – Aug.) • Functional requirements (Aug. – Dec.) • Subsystem design (Sept. – Dec.) • Proposals to TSIP & ATI • Plus: completion of two performance budgets, incorporation of additional atmospheric characterization data, & summary reports for the performance budgets & trade studies

  3. System Design Milestones Requirements  Performance Budgets + Trade Studies  System Architecture + Functional Requirements  Subsystem Design + Functional Requirements  Management Plan 4 milestones completed since June SSC meeting

  4. Schedule & Budget Schedule: 53% of System Design Phase work complete through Oct.

  5. Schedule & Budget Budget: 64% of System Design Phase budget ($730k) spent through Sept. • 92% of the $798k FY07 budget, excluding $20k contingency Plan needs to be reviewed to ensure deliverables complete for SDR

  6. Schedule & Budget

  7. TSIP & ATI Proposals • $2M TSIP proposal for NGAO preliminary design submitted on Aug. 31 • $2M request to fund ~70% of preliminary design • Detailed schedule/budget to be determined during system design • $1.1M ATI proposal for deployable near-IR integral field spectrograph system design submitted on Nov. 1 • Proposed to ATI program because • Most complex NGAO instrument, with longest lead time • Advanced nature of key components made it suitable for ATI • System design scheduled from May/08 to Dec/09 • Proposal writing in both cases led by Adkins with support from WMKO management & NGAO EC

  8. Design Teams • AO opto-mechanical (Lead - Gavel) • AO wavefront sensors (Velur) • AO operational tools (Neyman) • Laser facility (Chin) • Controls (Johansson) • Science operations (Le Mignant) • Work scope planning sheets (21) produced for all major design tasks • Define tasks, approach, inputs, products & personnel • Ensure agreement on scope • Some approvals are still pending

  9. WSPS Status All but the following WSPS have been approved: • AO opto-mechanical • 3.2.1 AO system architecture • ? • 3.2.2 AO enclosure • Revisions requested • 3.2.3 AO opto-mechanical • Revisions requested • AO operational tools • 3.2.3.12 PSF monitoring camera • Revision received, but effort has grown by 20h • Controls (Johansson) • 3.2.4.1 & 2 Non RTC software & electronics • Revisions recently received • Science operations (Le Mignant) • 3.4.2.1 & 2 AO-Instrument operations architecture & optimization • Low priority since WSPSs for currently active WBS approved

  10. Summary • Major milestones, except for science/system requirements, are being met • Good progress on functional requirements & database to maintain them • Schedule is starting to slip. • EC will be reviewing schedule & deliverables to ensure SDR is held on schedule & within budget