2023 COLOMBIAN POWER SYSTEM EXPANSION PLAN
E N D
2023 COLOMBIAN POWER SYSTEM EXPANSION PLAN WistonAndresÑustes Cuellar
Agenda • Powerdemand in Colombia • Generationprojection in Colombia • Transmissionprojection • Powersystemone-line diagramsfor 2023 • Conclusions • References
Powerdemand in Colombia • Maximumpower in 2007 (December): 9,079 MW • Maximumpowerin 2008 (December): 9,093 MW
Powerdemand in Colombia Currentaveragepower: 10MW Averagepowerfor2023: 15MW
Generationprojection in Colombia • ProjectedCapacity: 13545,8 MW • HidraulicProjects: 7685.5 MW • Coal projects: 2520.5 MW • Natural gas projects: 305 MW • Projects of fuel oil: 70.4 MW • Cogeneration projects: 44.9 MW • Wind projects: 20 MW
Generationprojection in Colombia Hidroelectric: Coal:
Generationprojection in Colombia Developingprojects:
Conclusions • The low demand scenario implies an additional required capacity after 2020. • 230 kV substation short circuit capacity is higher than 500 kV substations. • The Colombian power system will have large hydroelectric generation plants as Ituango, Quimbo, Sogamoso, and substations like Bosque, Porce III, Nueva Esperanza • Into the generations projects that we saw, Ituango will have the biggest generation with a capacity of 1,2 GW.
References [1] Upme, Plan de expansión de referencia Generación-Transmisión, 2009. [2] http://www1.upme.gov.co/ [3] http://www.creg.gov.co/html/i_portals/index.php [4] http://www.portafolio.co/economia/